Commuter Route 120 Expansion IT Equipment

Description: Expanding commuter route 120 and adding bus service to that area.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Riverside
City Beaumont
Zip Code 92223
 
Senate District
23
Assembly District 42
Congressional District 36
 
Caltrans District
08
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  50    100  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
CELINA CABRERA (951) 769-8522 X468   CCABRERA@CI.BEAUMONT.CA.US
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-Interest
$0 $0 $0
PTMISEA-99313
$5 $0 $5
Non-bond Funding
 
Total**** $5 $0 $6

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$5 $0 $6 $6 $6 $0
 
Total* $5 $0 $6 $6 $6 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
 

 
 

 
07/12/2017 

12/31/2017 
100   

 


Begin Closeout Phase

End Closeout Phase
 

 
05/28/2019 

05/28/2019 
03/28/2019 

04/29/2019 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 50 100

Bond Funding Cost
Adopted:
$5,066
Current Approved:
$5,066
Actual Expenditures:
$5,066

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31