Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
I-110 Freeway Access Ramp State Route 47 and 110 Northbound Connector Widening |
Description: Ramp Improvements
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
Project Location | |
---|---|
County |
Los Angeles |
City | Wilmington |
Zip Code | |
Senate District |
25 |
Assembly District | 54 |
Congressional District | 46 |
Caltrans District |
07 |
County/State Route | Los Angeles 47 |
Postmile Begin/End | 0 0.7 |
County/State Route | Los Angeles 110 |
Postmile Begin/End | 0.9 2 |
County/State Route | Los Angeles 110 |
Postmile Begin/End | 2.5 3 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Ramp/Connectors Lane Miles | 2.25 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Port of Los Angeles | Brian Correa | (310) 732-3643 | bcorrea@portla.org | |
Design (PS&E) Phase |
Port of Los Angeles | Brian Correa | (310) 732-3643 | bcorrea@portla.org | |
Right of Way Phase |
Port of Los Angeles | Brian Correa | (310) 732-3643 | bcorrea@portla.org | |
Construction Phase |
Port of Los Angeles | Brian Correa | (310) 732-3643 | bcorrea@portla.org | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
TCIF |
$14,700 | $-1,495 | $13,205 | ||||
Ports Inf, Sec, & AQ |
$2,052 | $14,495 | $16,547 | ||||
Non-bond Funding | |||||||
State/Federal* |
$22,547 | $-22,547 | $0 | ||||
Local** |
$11,420 | $-399 | $11,021 | ||||
Total**** | $50,719 | $-9,946 | $40,773 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$859 | $-159 | $700 | $0 | $0 | $700 | |
Design(PS&E) |
$4,168 | $1,400 | $5,568 | $0 | $0 | $5,568 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$45,692 | $-11,187 | $34,505 | $31,296 | $0 | $34,505 | |
Total* | $50,719 | $-9,946 | $40,773 | $31,296 | $0 | $40,773 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
07/01/2008 08/30/2009 |
06/27/2012 |
07/01/2008 05/30/2012 |
100 | 07/01/2008 05/30/2012 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
07/01/2008 03/31/2011 |
06/27/2012 |
07/01/2008 02/28/2013 |
100 | 07/01/2008 02/28/2013 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
09/01/2011 08/30/2014 |
06/27/2012 06/27/2012 |
06/30/2013 06/30/2015 |
100 | 07/12/2013 06/30/2016 |
0 -12 |
Begin Closeout Phase
End Closeout Phase |
09/01/2014 08/31/2015 |
06/27/2012 |
06/30/2015 06/30/2016 |
0 | 07/01/2016 05/01/2017 |
-12 -10 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Ramp/Connectors Lane Miles | 2.25 |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.