Caltrans Logo

I-110 Freeway Access Ramp State Route 47 and 110 Northbound Connector Widening

Description: Ramp Improvements

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
Project Location
County
Los Angeles
City Wilmington
Zip Code
 
Senate District
25
Assembly District 54
Congressional District 46
 
Caltrans District
07
 
 
County/State Route Los Angeles 47
Postmile Begin/End 0 0.7
 
County/State Route Los Angeles 110
Postmile Begin/End 0.9 2
 
County/State Route Los Angeles 110
Postmile Begin/End 2.5 3
Project Benefits
 Benefit Baseline Actual
Ramp/Connectors Lane Miles  2.25      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Port of Los Angeles Brian Correa (310) 732-3643   bcorrea@portla.org
Design (PS&E) Phase
Port of Los Angeles Brian Correa (310) 732-3643   bcorrea@portla.org
Right of Way Phase
Port of Los Angeles Brian Correa (310) 732-3643   bcorrea@portla.org
Construction Phase
Port of Los Angeles Brian Correa (310) 732-3643   bcorrea@portla.org
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TCIF
$14,700 $-1,495 $13,205
Ports Inf, Sec, & AQ
$2,052 $14,495 $16,547
Non-bond Funding
State/Federal*
$22,547 $-22,547 $0
Local**
$11,420 $-399 $11,021
 
Total**** $50,719 $-9,946 $40,773

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$859 $-159 $700 $0 $0 $700
Design(PS&E)
$4,168 $1,400 $5,568 $0 $0 $5,568
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$45,692 $-11,187 $34,505 $31,296 $0 $34,505
 
Total* $50,719 $-9,946 $40,773 $31,296 $0 $40,773

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
07/01/2008 

08/30/2009 
 

06/27/2012 
07/01/2008 

05/30/2012 
100  07/01/2008 

05/30/2012 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/01/2008 

03/31/2011 
 

06/27/2012 
07/01/2008 

02/28/2013 
100  07/01/2008 

02/28/2013 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
09/01/2011 

08/30/2014 
06/27/2012 

06/27/2012 
06/30/2013 

06/30/2015 
100  07/12/2013 

06/30/2016 


-12 
Begin Closeout Phase

End Closeout Phase
09/01/2014 

08/31/2015 
06/27/2012 

 
06/30/2015 

06/30/2016 
07/01/2016 

05/01/2017 
-12 

-10 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Ramp/Connectors Lane Miles 2.25

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.