Interim San Luis Obispo Layover Facility Expansion

Description: Final Design and Construction of additional trackage at San Luis Obispo Station

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
Project Location
County
San Luis Obispo, Z-Intercity Rai
City San Luis Obispo
Zip Code 93401
 
Senate District
17
Assembly District 35
Congressional District 24
 
Caltrans District
05
 
 
County/State Route San Luis Obispo PS
Postmile Begin/End 274.7 274.7
CC = Capital Corridor
PS = Pacific Surfliner
SJ = San Joaquin
Project Benefits
 Benefit Baseline Actual
Increase in Intercity Rail Round Trips  1      
Increase in Transit Ridership  1      
Increased Revenue Seating Capacity  1      
System Enhancement  1      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
LOSSAN Rail Corridor Agency Russ Henry 714-560-5990   RHenry@octa.net
Right of Way Phase
 
Construction Phase
LOSSAN Rail Corridor Agency Russ Henry 714-560-5990   RHenry@octa.net
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
RAIL
$1,600 $-1,300 $300
Non-bond Funding
 
Total**** $1,600 $-1,300 $300

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$300 $0 $300 $300 $300 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$1,300 $-1,300 $0 $0 $0 $0
 
Total* $1,600 $-1,300 $300 $300 $300 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

04/15/2020 
 

01/21/2021 
 

04/15/2020 
100   

04/14/2020 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
08/01/2020 

10/31/2020 
01/21/2021 

01/21/2021 
08/01/2021 

10/31/2021 
100  08/01/2021 

03/31/2022 


-5 
Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
11/01/2020 

01/31/2021 
01/21/2021 

01/21/2021 
11/01/2021 

01/31/2022 
 

 


Begin Closeout Phase

End Closeout Phase
02/01/2021 

07/30/2021 
01/21/2021 

01/21/2021 
02/01/2022 

07/31/2022 
02/01/2022 

12/31/2023 


-17 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase in Intercity Rail Round Trips 1
Increase in Transit Ridership 1
Increased Revenue Seating Capacity 1
System Enhancement 1

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.