Los Alamos Creek Bridge (Narlon) Replacement

Description: Track infrastructure and construct a replacement bridge with the same or similiar materials and design to the existing 124-year old steel trestle

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Santa Barbara
City Lompoc
Zip Code 93437
 
Senate District
19
Assembly District 35
Congressional District 24
 
Caltrans District
05
 
 
County/State Route Santa Barbara PS
Postmile Begin/End 291.3 291.3
CC = Capital Corridor
PS = Pacific Surfliner
SJ = San Joaquin
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)  1    1  
Increase in Transit Ridership  1    1  
MPH Increase in Project Area  1    1  
System Enhancement  1    1  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
 
Right of Way Phase
 
Construction Phase
LOSSAN Rail Corridor Agency Russ Henry 714-560-5990   rhenry@octa.net
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
RAIL
$15,526 $0 $15,526
Non-bond Funding
State/Federal*
$6,474 $0 $6,474
 
Total**** $22,000 $0 $22,000

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$22,000 $0 $22,000 $21,372 $21,372 $628
 
Total* $22,000 $0 $22,000 $21,372 $21,372 $628

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
08/30/2019 

10/17/2019 
12/31/2020 

12/31/2020 
08/30/2019 

10/17/2019 
100  08/30/2019 

10/17/2019 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/01/2019 

10/31/2019 
12/31/2020 

12/31/2020 
01/01/2019 

10/31/2019 
100  01/01/2019 

10/31/2019 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
04/01/2020 

06/30/2021 
12/31/2020 

06/30/2022 
08/01/2020 

12/31/2022 
95  08/01/2020 

12/31/2022 


Begin Closeout Phase

End Closeout Phase
07/01/2021 

12/31/2021 
06/30/2022 

06/30/2022 
01/01/2023 

02/29/2024 
01/01/2023 

02/29/2024 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 1 1
Increase in Transit Ridership 1 1
MPH Increase in Project Area 1 1
System Enhancement 1 1

Bond Funding Cost
Adopted:
$15,526,000
Current Approved:
$15,526,000
Actual Expenditures:
$15,526,000

 

Status as of December 31, 2023.