Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
C Street Access Ramps Improvement |
Description: Reconfigure and Modify Interchanges
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Los Angeles |
City | Wilmington |
Zip Code | |
Senate District |
25 |
Assembly District | 54 |
Congressional District | 46 |
Caltrans District |
07 |
County/State Route | Los Angeles 110 |
Postmile Begin/End |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Modified or Improved Interchanges (Nbr Modified) | 1 | 1 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Port of Los Angeles | Mimi Gutierrez | (310) 732-3339 | gutierrezmi@portla.org | |
Design (PS&E) Phase |
Port of Los Angeles | Mimi Gutierrez | (310) 732-3339 | gutierrezmi@portla.org | |
Right of Way Phase |
Port of Los Angeles | Mimi Gutierrez | (310) 732-3339 | gutierrezmi@portla.org | |
Construction Phase |
Port of Los Angeles | Mimi Gutierrez | (310) 732-3339 | gutierrezmi@portla.org | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
TCIF |
$8,300 | $-464 | $7,836 | ||||
Ports Inf, Sec, & AQ |
$1,260 | $16,918 | $18,178 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $5,766 | $5,766 | ||||
Local** |
$19,721 | $-13,074 | $6,647 | ||||
Total**** | $29,281 | $9,146 | $38,427 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$660 | $27 | $687 | $687 | $0 | $687 | |
Design(PS&E) |
$2,550 | $941 | $3,491 | $3,491 | $0 | $3,491 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$26,071 | $8,178 | $34,249 | $34,248 | $0 | $34,249 | |
Total* | $29,281 | $9,146 | $38,427 | $38,427 | $0 | $38,427 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
07/01/2008 08/30/2009 |
06/27/2012 |
07/01/2008 05/30/2012 |
100 | 07/01/2008 06/14/2012 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
07/01/2008 03/31/2011 |
05/07/2013 |
07/01/2008 03/29/2013 |
100 | 07/01/2008 03/29/2013 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
03/01/2012 02/28/2015 |
05/07/2013 05/07/2013 |
11/01/2013 10/31/2016 |
100 | 11/07/2013 04/30/2017 |
0 -6 |
Begin Closeout Phase
End Closeout Phase |
03/01/2015 02/28/2016 |
05/07/2013 |
11/01/2016 04/30/2017 |
50 | 05/01/2017 12/31/2018 |
-6 -20 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Modified or Improved Interchanges (Nbr Modified) | 1 | 1 |
Bond Funding Cost | |
---|---|
Adopted: |
$9,560,000 |
Current Approved: |
$8,300,000 |
Actual Expenditures: |
$7,835,676 |
Status as of December 31, 2023.