Caltrans Logo

Gerald Desmond Bridge Replacement

Description: Replace Bridge and Associated Approach Spans at Interchanges and Ramps

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
Project Location
County
Los Angeles
City Long Beach
Zip Code
 
Senate District
27
Assembly District 54
Congressional District 46
 
Caltrans District
07
 
 
County/State Route Los Angeles 710
Postmile Begin/End 3.7 5.8
Project Benefits
 Benefit Baseline Actual
New Bridges (Nbr)  1      
New Interchanges (Nbr Constructed)  2      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Port of Long Beach M. J. Bogner (562) 590-4146   bogner@polb.com
Design (PS&E) Phase
Port of Long Beach Eric Shen (562) 590-4155   shen@polb.com
Right of Way Phase
Port of Long Beach Eric Shen (562) 590-4155   shen@polb.com
Construction Phase
Port of Long Beach Eric Shen (562) 590-4155   shen@polb.com
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
CMIA
$0 $153,657 $153,657
TCIF
$250,000 $49,795 $299,795
Non-bond Funding
State/Federal*
$6,100 $729,658 $735,758
Local**
$869,100 $-722,249 $146,851
 
Total**** $1,125,200 $210,861 $1,336,061

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$29,300 $-17,438 $11,862 $0 $0 $11,862
Design(PS&E)
$37,000 $1,239 $38,239 $0 $0 $38,239
Right of Way
$110,800 $213,900 $324,700 $0 $0 $324,700
Construction
$948,100 $13,160 $961,260 $0 $0 $961,260
 
Total* $1,125,200 $210,861 $1,336,061 $0 $0 $1,336,061

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
03/29/2003 

06/01/2009 
 

11/03/2010 
03/29/2003 

08/09/2010 
100   

09/22/2010 


-1 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
06/02/2009 

09/01/2010 
09/27/2012 

11/03/2010 
08/16/2012 

06/07/2013 
91  08/16/2012 

 


Begin Right of Way Phase

End Right of Way Phase
06/02/2009 

09/01/2010 
09/27/2012 

09/27/2012 
03/01/2011 

12/31/2012 
85   

12/31/2012 


Begin Construction Phase

End Construction Phase
12/01/2010 

09/01/2015 
09/27/2012 

09/27/2012 
06/07/2013 

06/27/2016 
96  06/11/2013 

10/27/2018 


-28 
Begin Closeout Phase

End Closeout Phase
09/01/2015 

06/01/2016 
09/27/2012 

 
06/27/2016 

09/26/2016 
10/27/2018 

01/01/2019 
-28 

-28 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
New Bridges (Nbr) 1
New Interchanges (Nbr Constructed) 2

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.