Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Gerald Desmond Bridge Replacement |
Description: Replace Bridge and Associated Approach Spans at Interchanges and Ramps
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
Project Location | |
---|---|
County |
Los Angeles |
City | Long Beach |
Zip Code | |
Senate District |
27 |
Assembly District | 54 |
Congressional District | 46 |
Caltrans District |
07 |
County/State Route | Los Angeles 710 |
Postmile Begin/End | 3.7 5.8 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
New Bridges (Nbr) | 1 | |
New Interchanges (Nbr Constructed) | 2 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Port of Long Beach | M. J. Bogner | (562) 590-4146 | bogner@polb.com | |
Design (PS&E) Phase |
Port of Long Beach | Eric Shen | (562) 590-4155 | shen@polb.com | |
Right of Way Phase |
Port of Long Beach | Eric Shen | (562) 590-4155 | shen@polb.com | |
Construction Phase |
Port of Long Beach | Eric Shen | (562) 590-4155 | shen@polb.com | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
CMIA |
$0 | $153,657 | $153,657 | ||||
TCIF |
$250,000 | $49,795 | $299,795 | ||||
Non-bond Funding | |||||||
State/Federal* |
$6,100 | $729,658 | $735,758 | ||||
Local** |
$869,100 | $-722,249 | $146,851 | ||||
Total**** | $1,125,200 | $210,861 | $1,336,061 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$29,300 | $-17,438 | $11,862 | $0 | $0 | $11,862 | |
Design(PS&E) |
$37,000 | $1,239 | $38,239 | $0 | $0 | $38,239 | |
Right of Way |
$110,800 | $213,900 | $324,700 | $0 | $0 | $324,700 | |
Construction |
$948,100 | $13,160 | $961,260 | $0 | $0 | $961,260 | |
Total* | $1,125,200 | $210,861 | $1,336,061 | $0 | $0 | $1,336,061 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
03/29/2003 06/01/2009 |
11/03/2010 |
03/29/2003 08/09/2010 |
100 | 09/22/2010 |
0 -1 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
06/02/2009 09/01/2010 |
09/27/2012 11/03/2010 |
08/16/2012 06/07/2013 |
91 | 08/16/2012 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
06/02/2009 09/01/2010 |
09/27/2012 09/27/2012 |
03/01/2011 12/31/2012 |
85 | 12/31/2012 |
0 0 |
Begin Construction Phase
End Construction Phase |
12/01/2010 09/01/2015 |
09/27/2012 09/27/2012 |
06/07/2013 06/27/2016 |
96 | 06/11/2013 10/27/2018 |
0 -28 |
Begin Closeout Phase
End Closeout Phase |
09/01/2015 06/01/2016 |
09/27/2012 |
06/27/2016 09/26/2016 |
0 | 10/27/2018 01/01/2019 |
-28 -28 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
New Bridges (Nbr) | 1 | |
New Interchanges (Nbr Constructed) | 2 |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.