Caltrans Logo

Lakeview Avenue Overcrossing

Description: Construct Grade Separation

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Orange
City
Zip Code
 
Senate District
29
Assembly District 79
Congressional District 42
 
Caltrans District
12
 
Project Benefits
 Benefit Baseline Actual
Rail At-Grade Crossings Eliminated      1  
Rail/Highway At-Grade Crossings Eliminated  1    1  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Placentia Michael McConaha (714) 993-8245   MMcConaha@placentia.org
Design (PS&E) Phase
Orange County Transportation Authority Joel Toolson (714) 560-5406   jtoolson@octa.net
Right of Way Phase
Orange County Transportation Authority Joel Toolson (714) 560-5406   jtoolson@octa.net
Construction Phase
Orange County Transportation Authority Joel Toolson (714) 560-5406   jtoolson@octa.net
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TCIF
$28,685 $-1,165 $27,520
Non-bond Funding
Local**
$29,840 $33,789 $63,629
 
Total**** $58,525 $32,624 $91,149

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$2,494 $-1,863 $631 $631 $631 $0
Design(PS&E)
$2,868 $4,999 $7,867 $6,831 $6,831 $1,036
Right of Way
$24,478 $15,210 $39,688 $49,093 $49,093 $-9,405
Construction
$28,685 $14,278 $42,963 $43,307 $43,307 $-344
 
Total* $58,525 $32,624 $91,149 $99,861 $99,861 $-8,712

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
01/01/2001 

12/01/2008 
 

05/11/2011 
01/01/2001 

09/23/2009 
100  01/01/2001 

09/23/2009 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/01/2009 

06/01/2011 
05/11/2011 

03/05/2013 
02/06/2009 

01/14/2013 
100  02/06/2009 

01/14/2013 


Begin Right of Way Phase

End Right of Way Phase
10/01/2009 

12/01/2010 
05/11/2011 

05/11/2011 
04/01/2011 

01/01/2013 
100  04/01/2011 

01/14/2013 


Begin Construction Phase

End Construction Phase
07/01/2011 

01/01/2014 
03/05/2013 

05/11/2011 
09/01/2013 

12/01/2015 
100  11/25/2013 

06/05/2017 
-3 

-18 
Begin Closeout Phase

End Closeout Phase
01/01/2014 

01/01/2017 
03/05/2013 

 
12/01/2015 

12/01/2018 
100  06/06/2017 

12/01/2018 
-18 

????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Rail At-Grade Crossings Eliminated 1
Rail/Highway At-Grade Crossings Eliminated 1 1

Bond Funding Cost
Adopted:
$28,685,000
Current Approved:
$27,520,000
Actual Expenditures:
$27,344,133

 

Status as of December 31, 2023.