Iowa Avenue Grade Separation

Description: Construct Grade Separation

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Riverside
City Riverside
Zip Code 92507
 
Senate District
31
Assembly District 61
Congressional District 41
 
Caltrans District
08
 
Project Benefits
 Benefit Baseline Actual
Rail At-Grade Crossings Eliminated      1  
Rail/Highway At-Grade Crossings Eliminated  1      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
City of Riverside Debbie Anderson (951) 826-5517   danderson@riversideca.gov
Design (PS&E) Phase
City of Riverside Debbie Anderson (951) 826-5517   danderson@riversideca.gov
Right of Way Phase
City of Riverside Debbie Anderson (951) 826-5517   danderson@riversideca.gov
Construction Phase
City of Riverside Debbie Anderson (951) 826-5517   danderson@riversideca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TCIF
$13,000 $0 $13,000
Non-bond Funding
State/Federal*
$11,380 $-2,000 $9,380
Local**
$7,620 $600 $8,220
Private***
$0 $1,400 $1,400
 
Total**** $32,000 $0 $32,000

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$500 $0 $500 $500 $500 $-0
Design(PS&E)
$1,500 $0 $1,500 $1,424 $1,424 $76
Right of Way
$5,500 $0 $5,500 $6,851 $6,851 $-1,351
Construction
$24,500 $0 $24,500 $19,529 $19,529 $4,971
 
Total* $32,000 $0 $32,000 $28,305 $28,305 $3,695

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
08/01/2007 

07/01/2008 
 

 
08/01/2007 

07/01/2008 
100  08/01/2007 

07/31/2008 


-1 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
08/01/2008 

03/01/2010 
 

10/26/2011 
08/01/2008 

09/30/2011 
100  08/01/2008 

09/30/2011 


Begin Right of Way Phase

End Right of Way Phase
11/01/2008 

03/01/2010 
 

10/26/2011 
11/01/2008 

08/19/2011 
100  05/28/2009 

08/19/2011 
-7 

Begin Construction Phase

End Construction Phase
07/01/2010 

11/01/2011 
04/25/2012 

04/25/2012 
06/26/2012 

11/01/2013 
100  06/26/2012 

04/21/2014 


-6 
Begin Closeout Phase

End Closeout Phase
11/01/2011 

05/01/2012 
04/25/2012 

 
11/01/2013 

05/01/2014 
100  05/01/2014 

05/03/2019 
-6 

-61 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Rail At-Grade Crossings Eliminated 1
Rail/Highway At-Grade Crossings Eliminated 1

Bond Funding Cost
Adopted:
$13,000,000
Current Approved:
$10,320,000
Actual Expenditures:
$10,320,000

 

Status as of December 31, 2023.