Sunset Avenue Grade Separation

Description: Construct Grade Separation

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Riverside
City Banning
Zip Code 92220
 
Senate District
23
Assembly District 42
Congressional District 36
 
Caltrans District
08
 
Project Benefits
 Benefit Baseline Actual
Rail At-Grade Crossings Eliminated      1  
Rail/Highway At-Grade Crossings Eliminated  1    1  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
City of Banning Kahono Oei (951) 922-3130   koei@ci.banning.ca.us
Design (PS&E) Phase
City of Banning Kahono Oei (951) 922-3130   koei@ci.banning.ca.us
Right of Way Phase
City of Banning Kahono Oei (951) 922-3130   koei@ci.banning.ca.us
Construction Phase
County of Riverside C. Scotty Staley (951) 955-2092   cstaley@rctlma.org
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TCIF
$10,000 $-1,722 $8,278
Non-bond Funding
State/Federal*
$3,100 $-1,618 $1,482
Local**
$23,400 $-118 $23,282
 
Total**** $36,500 $-3,458 $33,042

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$400 $500 $900 $84 $84 $816
Design(PS&E)
$4,100 $-1,800 $2,300 $3,318 $3,318 $-1,018
Right of Way
$1,100 $42 $1,142 $806 $806 $336
Construction
$30,900 $-2,200 $28,700 $25,850 $25,850 $2,850
 
Total* $36,500 $-3,458 $33,042 $30,059 $30,059 $2,983

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
01/01/2006 

12/01/2009 
 

03/05/2013 
01/01/2006 

02/28/2011 
100  01/01/2007 

03/01/2011 
-12 

Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/01/2010 

07/01/2011 
03/05/2013 

06/11/2013 
05/10/2011 

05/15/2013 
100  03/01/2011 

03/07/2013 


Begin Right of Way Phase

End Right of Way Phase
01/01/2010 

07/01/2011 
03/05/2013 

06/11/2013 
05/10/2011 

05/30/2013 
100  05/10/2011 

04/09/2013 


Begin Construction Phase

End Construction Phase
01/15/2012 

12/31/2014 
06/11/2013 

06/11/2013 
12/01/2013 

02/28/2016 
100  12/03/2013 

12/11/2018 


-34 
Begin Closeout Phase

End Closeout Phase
01/01/2015 

07/01/2015 
06/11/2013 

 
03/01/2016 

08/01/2016 
100  01/01/2020 

06/01/2020 
-47 

-47 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Rail At-Grade Crossings Eliminated 1
Rail/Highway At-Grade Crossings Eliminated 1 1

Bond Funding Cost
Adopted:
$10,000,000
Current Approved:
$10,000,000
Actual Expenditures:
$7,388,000

 

Status as of December 31, 2023.