Avenue 56 Grade Separation Union Pacific Yuma Subdivision

Description: Construct Grade Separation

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Riverside
City
Zip Code
 
Senate District
28
Assembly District 56
Congressional District 36
 
Caltrans District
08
 
Project Benefits
 Benefit Baseline Actual
Rail At-Grade Crossings Eliminated      1  
Rail/Highway At-Grade Crossings Eliminated  1    1  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
County of Riverside Scott Staley (951) 955-2092   cstaley@rivco.org
Design (PS&E) Phase
County of Riverside Scott Staley (951) 955-2092   cstaley@rivco.org
Right of Way Phase
County of Riverside Scott Staley (951) 955-2092   cstaley@rivco.org
Construction Phase
County of Riverside Scott Staley (951) 955-2092   cstaley@rivco.org
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TCIF
$10,000 $2,802 $12,802
Non-bond Funding
Local**
$50,000 $-33,408 $16,592
 
Total**** $60,000 $-30,606 $29,394

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$800 $-505 $295 $159 $159 $136
Design(PS&E)
$2,800 $-532 $2,268 $3,154 $3,154 $-886
Right of Way
$8,500 $-5,211 $3,289 $3,688 $3,688 $-399
Construction
$47,900 $-24,358 $23,542 $25,544 $25,544 $-2,002
 
Total* $60,000 $-30,606 $29,394 $32,545 $32,545 $-3,151

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
12/01/2008 

12/31/2010 
12/06/2012 

12/06/2012 
09/01/2010 

07/28/2011 
100  06/30/2009 

08/28/2011 
14 

-1 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/03/2011 

06/29/2012 
12/06/2012 

06/11/2013 
03/28/2011 

03/28/2013 
100  05/24/2011 

04/22/2013 
-2 

-1 
Begin Right of Way Phase

End Right of Way Phase
03/31/2011 

03/30/2012 
12/06/2012 

06/11/2013 
03/28/2011 

05/30/2013 
100  03/31/2011 

10/05/2013 


-4 
Begin Construction Phase

End Construction Phase
12/28/2012 

12/28/2014 
06/11/2013 

06/11/2013 
12/01/2013 

02/28/2016 
100  11/05/2013 

05/09/2017 


-15 
Begin Closeout Phase

End Closeout Phase
01/02/2015 

04/01/2015 
12/06/2012 

 
06/15/2016 

10/15/2016 
100  05/10/2018 

03/04/2022 
-23 

-66 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Rail At-Grade Crossings Eliminated 1
Rail/Highway At-Grade Crossings Eliminated 1 1

Bond Funding Cost
Adopted:
$10,000,000
Current Approved:
$12,802,000
Actual Expenditures:
$12,802,000

Click to view the Final Audit Report

 

Status as of December 31, 2023.