Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Fullerton Road Grade Separation Project |
Description: Construct 6-lane roadway underpass on Fullerton Road in the City of Industry on exsiting Union Pacific railroad tracks.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
Project Location | |
---|---|
County |
Los Angeles |
City | City Of Industry |
Zip Code | |
Senate District |
22 |
Assembly District | 57 |
Congressional District | 32 |
Caltrans District |
07 |
County/State Route | Los Angeles 60 |
Postmile Begin/End |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
System Enhancement | 115.4 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
|||||
Design (PS&E) Phase |
|||||
Right of Way Phase |
|||||
Construction Phase |
Caltrans | Carlos Ruiz | 916-654-3894 | carlos.ruiz@dot.ca.gov | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
TCIF |
$0 | $0 | $0 | ||||
HRCSA |
$0 | $18,306 | $18,306 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $5,000 | $5,000 | ||||
Local** |
$0 | $126,878 | $126,878 | ||||
Private*** |
$0 | $3,000 | $3,000 | ||||
Total**** | $0 | $153,184 | $153,184 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$0 | $10,747 | $10,747 | $10,698 | $10,698 | $49 | |
Right of Way |
$0 | $38,270 | $38,270 | $31,335 | $31,335 | $6,935 | |
Construction |
$0 | $104,167 | $104,167 | $97,020 | $97,020 | $7,147 | |
Total* | $0 | $153,184 | $153,184 | $139,053 | $139,053 | $14,131 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
11/01/2012 10/31/2013 |
01/22/2015 01/22/2015 |
11/01/2012 10/31/2013 |
100 | 11/13/2012 10/28/2013 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
11/01/2013 12/31/2015 |
01/22/2015 01/22/2015 |
11/01/2013 12/31/2015 |
100 | 11/01/2013 10/30/2015 |
0 2 |
Begin Right of Way Phase
End Right of Way Phase |
11/01/2013 12/31/2015 |
01/22/2015 01/22/2015 |
11/01/2013 12/31/2015 |
100 | 05/01/2013 10/08/2015 |
6 3 |
Begin Construction Phase
End Construction Phase |
03/01/2016 09/30/2019 |
01/22/2015 01/22/2015 |
03/01/2016 09/30/2019 |
62 | 07/01/2016 12/31/2024 |
-4 -64 |
Begin Closeout Phase
End Closeout Phase |
09/30/2019 03/31/2020 |
01/22/2015 01/22/2015 |
09/30/2019 03/31/2020 |
0 | 01/01/2025 06/30/2025 |
-64 -64 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
System Enhancement | 115.4 |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.