Fullerton Road Grade Separation Project

Description: Construct 6-lane roadway underpass on Fullerton Road in the City of Industry on exsiting Union Pacific railroad tracks.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
Project Location
County
Los Angeles
City City Of Industry
Zip Code
 
Senate District
22
Assembly District 57
Congressional District 32
 
Caltrans District
07
 
 
County/State Route Los Angeles 60
Postmile Begin/End
Project Benefits
 Benefit Baseline Actual
System Enhancement  115.4      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
 
Right of Way Phase
 
Construction Phase
Caltrans Carlos Ruiz 916-654-3894   carlos.ruiz@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TCIF
$0 $0 $0
HRCSA
$0 $18,306 $18,306
Non-bond Funding
State/Federal*
$0 $5,000 $5,000
Local**
$0 $126,878 $126,878
Private***
$0 $3,000 $3,000
 
Total**** $0 $153,184 $153,184

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $10,747 $10,747 $10,698 $10,698 $49
Right of Way
$0 $38,270 $38,270 $31,335 $31,335 $6,935
Construction
$0 $104,167 $104,167 $97,020 $97,020 $7,147
 
Total* $0 $153,184 $153,184 $139,053 $139,053 $14,131

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
11/01/2012 

10/31/2013 
01/22/2015 

01/22/2015 
11/01/2012 

10/31/2013 
100  11/13/2012 

10/28/2013 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
11/01/2013 

12/31/2015 
01/22/2015 

01/22/2015 
11/01/2013 

12/31/2015 
100  11/01/2013 

10/30/2015 


Begin Right of Way Phase

End Right of Way Phase
11/01/2013 

12/31/2015 
01/22/2015 

01/22/2015 
11/01/2013 

12/31/2015 
100  05/01/2013 

10/08/2015 


Begin Construction Phase

End Construction Phase
03/01/2016 

09/30/2019 
01/22/2015 

01/22/2015 
03/01/2016 

09/30/2019 
62  07/01/2016 

12/31/2024 
-4 

-64 
Begin Closeout Phase

End Closeout Phase
09/30/2019 

03/31/2020 
01/22/2015 

01/22/2015 
09/30/2019 

03/31/2020 
01/01/2025 

06/30/2025 
-64 

-64 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
System Enhancement 115.4

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.