March Inland Cargo Port Airport (I-215 and Van Buren Boulevard Ground Access Improvements)

Description: Mitigate Existing and Projected Capacity and Operational Deficiencies at I-215 Interchange

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Riverside
City
Zip Code
 
Senate District
37
Assembly District 64
Congressional District 45
 
Caltrans District
08
 
 
County/State Route Riverside 215
Postmile Begin/End R  32.3 R  35.9
Project Benefits
 Benefit Baseline Actual
Modified or Improved Interchanges (Nbr Modified)  1    1  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
MJPA Dan Fairbanks (951) 656-7000   fairbanks@marchjpa.com
Design (PS&E) Phase
County of Riverside John Marcinek (951) 955-3727   jmarcine@rctima.org
Right of Way Phase
County of Riverside John Marcinek (951) 955-3727   jmarcine@rctima.org
Construction Phase
County of Riverside John Marcinek (951) 955-3727   jmarcine@rctima.org
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TCIF
$10,000 $-1,165 $8,835
Non-bond Funding
Local**
$87,550 $-29,609 $57,941
 
Total**** $97,550 $-30,774 $66,776

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$3,550 $-87 $3,463 $3,222 $3,222 $241
Design(PS&E)
$5,500 $-714 $4,786 $4,957 $4,957 $-171
Right of Way
$7,000 $0 $7,000 $7,317 $7,317 $-317
Construction
$81,500 $-29,973 $51,527 $37,897 $37,897 $13,630
 
Total* $97,550 $-30,774 $66,776 $53,392 $53,392 $13,384

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
08/01/2005 

04/23/2009 
 

 
08/01/2005 

04/23/2009 
100  08/01/2005 

12/10/2009 


-8 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/07/2008 

08/26/2011 
 

09/15/2011 
07/07/2008 

09/01/2011 
100  07/07/2008 

09/01/2011 


Begin Right of Way Phase

End Right of Way Phase
04/24/2009 

08/11/2011 
 

09/15/2011 
04/24/2009 

09/01/2011 
100  03/04/2009 

09/01/2011 


Begin Construction Phase

End Construction Phase
01/02/2012 

12/26/2013 
09/15/2011 

09/15/2011 
04/30/2012 

04/30/2014 
100  08/13/2012 

05/28/2018 
-3 

-50 
Begin Closeout Phase

End Closeout Phase
12/30/2013 

04/30/2014 
09/15/2011 

 
04/30/2014 

09/30/2014 
100  05/28/2018 

07/20/2018 
-50 

-46 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Modified or Improved Interchanges (Nbr Modified) 1 1

Bond Funding Cost
Adopted:
$10,000,000
Current Approved:
$8,835,000
Actual Expenditures:
$6,450,485

 

Status as of December 31, 2023.