March Inland Cargo Port Airport (I-215 and Van Buren Boulevard Ground Access Improvements) |
Description: Mitigate Existing and Projected Capacity and Operational Deficiencies at I-215 Interchange
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Riverside |
City | |
Zip Code | |
Senate District |
37 |
Assembly District | 64 |
Congressional District | 45 |
Caltrans District |
08 |
County/State Route | Riverside 215 |
Postmile Begin/End | R 32.3 R 35.9 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Modified or Improved Interchanges (Nbr Modified) | 1 | 1 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
MJPA | Dan Fairbanks | (951) 656-7000 | fairbanks@marchjpa.com | |
Design (PS&E) Phase |
County of Riverside | John Marcinek | (951) 955-3727 | jmarcine@rctima.org | |
Right of Way Phase |
County of Riverside | John Marcinek | (951) 955-3727 | jmarcine@rctima.org | |
Construction Phase |
County of Riverside | John Marcinek | (951) 955-3727 | jmarcine@rctima.org | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
TCIF |
$10,000 | $-1,165 | $8,835 | ||||
Non-bond Funding | |||||||
Local** |
$87,550 | $-29,609 | $57,941 | ||||
Total**** | $97,550 | $-30,774 | $66,776 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$3,550 | $-87 | $3,463 | $3,222 | $3,222 | $241 | |
Design(PS&E) |
$5,500 | $-714 | $4,786 | $4,957 | $4,957 | $-171 | |
Right of Way |
$7,000 | $0 | $7,000 | $7,317 | $7,317 | $-317 | |
Construction |
$81,500 | $-29,973 | $51,527 | $37,897 | $37,897 | $13,630 | |
Total* | $97,550 | $-30,774 | $66,776 | $53,392 | $53,392 | $13,384 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
08/01/2005 04/23/2009 |
|
08/01/2005 04/23/2009 |
100 | 08/01/2005 12/10/2009 |
0 -8 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
07/07/2008 08/26/2011 |
09/15/2011 |
07/07/2008 09/01/2011 |
100 | 07/07/2008 09/01/2011 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
04/24/2009 08/11/2011 |
09/15/2011 |
04/24/2009 09/01/2011 |
100 | 03/04/2009 09/01/2011 |
2 0 |
Begin Construction Phase
End Construction Phase |
01/02/2012 12/26/2013 |
09/15/2011 09/15/2011 |
04/30/2012 04/30/2014 |
100 | 08/13/2012 05/28/2018 |
-3 -50 |
Begin Closeout Phase
End Closeout Phase |
12/30/2013 04/30/2014 |
09/15/2011 |
04/30/2014 09/30/2014 |
100 | 05/28/2018 07/20/2018 |
-50 -46 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Modified or Improved Interchanges (Nbr Modified) | 1 | 1 |
Bond Funding Cost | |
---|---|
Adopted: |
$10,000,000 |
Current Approved: |
$8,835,000 |
Actual Expenditures: |
$6,450,485 |
Status as of December 31, 2023.