Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Bridge No. 04C0104 - WADDINGTON RD & SALT RIVER |
|
Description: Bridge No. 04C0104 - WADDINGTON RD & SALT RIVER - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
| Project Location | |
|---|---|
| County |
Humboldt County |
| City | |
| Zip Code | 95536 |
| Senate District |
02 |
| Assembly District | 01 |
| Congressional District | 01 |
| Caltrans District |
01 |
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Bridge Seismically Retrofitted | N | Y |
| Project Contacts | Agency | Contact Person | Telephone | |
|---|---|---|---|---|
| Seismic |
Humboldt County | Tony Seghetti | (707) 445-7448 | tseghetti@co.humboldt.ca.us |
| Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (12/31/2025 b=c-a |
Current Approved (12/31/2025 c |
|||||
| Bond Funding | |||||||
| LBSRA |
$116 | $41 | $157 | ||||
| Non-bond Funding | |||||||
| State/Federal* |
$981 | $392 | $1,372 | ||||
| Local** |
$4 | $8 | $11 | ||||
| Private*** |
$0 | $0 | $0 | ||||
| Total**** | $1,100 | $440 | $1,540 | ||||
**** Totals may not add up exactly to column amounts due to rounding
| Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (12/31/2025 b=c-a |
Current Approved (12/31/2025 c |
Cost to Date** (12/31/2025 d |
Cost Forecast (12/31/2025 e |
Cost Variance f=c-e |
||
| Preliminary Engineering |
$90 | $-11 | $79 | $0 | $0 | $79 | |
| Right of Way |
$10 | $25 | $35 | $35 | $35 | $0 | |
| Construction |
$1,000 | $426 | $1,426 | $1,266 | $1,266 | $160 | |
| Total* | $1,100 | $440 | $1,540 | $1,301 | $1,301 | $240 | |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
| Project Schedule Baseline Summary | ||||||
|---|---|---|---|---|---|---|
| (Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2025) c |
% Complete (12/31/2025) d |
Schedule Forecast (12/31/2025) e |
Schedule Variance (months) f=c-e |
|
Begin Strategy Phase
End Strategy Phase |
09/30/1994 09/30/1998 |
|
09/30/1994 09/30/1998 |
100 | 09/30/1994 09/30/1998 |
0 0 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
09/30/2000 09/30/2011 |
10/15/2009 10/15/2009 |
09/30/2000 09/30/2011 |
100 | 09/30/2000 09/30/2011 |
0 0 |
|
Begin Right of Way Phase
End Right of Way Phase |
09/30/2008 09/30/2010 |
10/15/2009 10/15/2009 |
09/30/2008 06/30/2010 |
100 | 07/18/2011 03/09/2015 |
-34 -57 |
|
Begin Construction Phase
End Construction Phase |
06/30/2011 04/30/2012 |
10/15/2009 10/15/2009 |
06/30/2011 04/30/2012 |
100 | 03/25/2015 12/05/2017 |
-45 -68 |
|
Begin Closeout Phase
End Closeout Phase |
|
|
|
100 | 12/05/2017 09/07/2021 |
0 0 |
????????
No map available at this time.
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Bridge Seismically Retrofitted | N | Y |
| Bond Funding Cost | |
|---|---|
| Adopted: |
$115,847 |
| Current Approved: |
$156,646 |
| Actual Expenditures: |
$156,646 |
Status as of December 31, 2025.
