Caltrans Logo

I-10 and Cherry Avenue Interchange Reconstruction

Description: Improves Interchange

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Bernardino
City Fontana
Zip Code
 
Senate District
32
Assembly District 62
Congressional District 43
 
Caltrans District
08
 
 
County/State Route San Bernardino 10
Postmile Begin/End 12.5 13.8
Project Benefits
 Benefit Baseline Actual
Modified Bridges (Nbr Modified)  1    1  
New Bridges (Nbr)  1      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Caltrans Mark Lancaster (909) 659-7483   mark.lancaster@dot.ca.gov
Design (PS&E) Phase
SANBAG Marie Marston (909) 884-8276   mmarston@sanbag.ca.gov
Right of Way Phase
City of Fontana Kevin Ryan (909) 350-6655   Kryan@fontana.org
Construction Phase
SANBAG Marie Marston (909) 884-8276   mmarston@sanbag.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TCIF
$30,773 $-2,151 $28,622
Non-bond Funding
State/Federal*
$3,908 $-3,908 $0
Local**
$43,125 $5,390 $48,515
 
Total**** $77,806 $-669 $77,137

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$935 $-154 $781 $781 $781 $0
Design(PS&E)
$5,822 $530 $6,352 $6,352 $6,352 $0
Right of Way
$9,503 $3,500 $13,003 $13,003 $13,003 $0
Construction
$61,546 $-4,545 $57,001 $57,000 $57,000 $1
 
Total* $77,806 $-669 $77,137 $77,136 $77,136 $1

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
09/30/2005 

03/31/2009 
 

 
09/30/2005 

03/31/2009 
100  09/30/2005 

03/12/2009 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
02/15/2008 

12/31/2010 
 

 
02/15/2008 

12/31/2010 
100  02/15/2008 

07/01/2011 


-6 
Begin Right of Way Phase

End Right of Way Phase
04/01/2009 

04/01/2011 
 

 
04/01/2009 

04/01/2011 
100  04/01/2009 

07/01/2011 


-3 
Begin Construction Phase

End Construction Phase
08/01/2011 

12/31/2013 
 

 
08/01/2011 

12/31/2013 
100  10/03/2012 

05/07/2016 
-14 

-29 
Begin Closeout Phase

End Closeout Phase
12/31/2013 

06/30/2014 
 

 
12/31/2013 

06/30/2014 
100  05/08/2016 

12/29/2017 
-29 

-43 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Modified Bridges (Nbr Modified) 1 1
New Bridges (Nbr) 1

Bond Funding Cost
Adopted:
$30,773,000
Current Approved:
$30,773,000
Actual Expenditures:
$28,621,251

 

Status as of December 31, 2023.