I-10 and Cherry Avenue Interchange Reconstruction |
Description: Improves Interchange
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Bernardino |
City | Fontana |
Zip Code | |
Senate District |
32 |
Assembly District | 62 |
Congressional District | 43 |
Caltrans District |
08 |
County/State Route | San Bernardino 10 |
Postmile Begin/End | 12.5 13.8 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Modified Bridges (Nbr Modified) | 1 | 1 |
New Bridges (Nbr) | 1 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Caltrans | Mark Lancaster | (909) 659-7483 | mark.lancaster@dot.ca.gov | |
Design (PS&E) Phase |
SANBAG | Marie Marston | (909) 884-8276 | mmarston@sanbag.ca.gov | |
Right of Way Phase |
City of Fontana | Kevin Ryan | (909) 350-6655 | Kryan@fontana.org | |
Construction Phase |
SANBAG | Marie Marston | (909) 884-8276 | mmarston@sanbag.ca.gov | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
TCIF |
$30,773 | $-2,151 | $28,622 | ||||
Non-bond Funding | |||||||
State/Federal* |
$3,908 | $-3,908 | $0 | ||||
Local** |
$43,125 | $5,390 | $48,515 | ||||
Total**** | $77,806 | $-669 | $77,137 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$935 | $-154 | $781 | $781 | $781 | $0 | |
Design(PS&E) |
$5,822 | $530 | $6,352 | $6,352 | $6,352 | $0 | |
Right of Way |
$9,503 | $3,500 | $13,003 | $13,003 | $13,003 | $0 | |
Construction |
$61,546 | $-4,545 | $57,001 | $57,000 | $57,000 | $1 | |
Total* | $77,806 | $-669 | $77,137 | $77,136 | $77,136 | $1 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
09/30/2005 03/31/2009 |
|
09/30/2005 03/31/2009 |
100 | 09/30/2005 03/12/2009 |
0 1 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
02/15/2008 12/31/2010 |
|
02/15/2008 12/31/2010 |
100 | 02/15/2008 07/01/2011 |
0 -6 |
Begin Right of Way Phase
End Right of Way Phase |
04/01/2009 04/01/2011 |
|
04/01/2009 04/01/2011 |
100 | 04/01/2009 07/01/2011 |
0 -3 |
Begin Construction Phase
End Construction Phase |
08/01/2011 12/31/2013 |
|
08/01/2011 12/31/2013 |
100 | 10/03/2012 05/07/2016 |
-14 -29 |
Begin Closeout Phase
End Closeout Phase |
12/31/2013 06/30/2014 |
|
12/31/2013 06/30/2014 |
100 | 05/08/2016 12/29/2017 |
-29 -43 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Modified Bridges (Nbr Modified) | 1 | 1 |
New Bridges (Nbr) | 1 |
Bond Funding Cost | |
---|---|
Adopted: |
$30,773,000 |
Current Approved: |
$30,773,000 |
Actual Expenditures: |
$28,621,251 |
Status as of December 31, 2023.