Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Bridge No. 50C0123 - OLD RIVER RD & OLD RIVER ROAD |
|
Description: Bridge No. 50C0123 - OLD RIVER RD & OLD RIVER ROAD - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
| Project Location | |
|---|---|
| County |
Kern County |
| City | |
| Zip Code | 93313 |
| Senate District |
18 |
| Assembly District | 32 |
| Congressional District | 22 |
| Caltrans District |
06 |
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Bridge Seismically Retrofitted | N | |
| Project Contacts | Agency | Contact Person | Telephone | |
|---|---|---|---|---|
| Seismic |
Department of Water Resources | Ray Miller | (916) 653-9443 | rhmiller@water.ca.gov |
| Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (12/31/2025 b=c-a |
Current Approved (12/31/2025 c |
|||||
| Bond Funding | |||||||
| LBSRA |
$17 | $1 | $18 | ||||
| Non-bond Funding | |||||||
| State/Federal* |
$253 | $9 | $262 | ||||
| Local** |
$30 | $0 | $30 | ||||
| Private*** |
$0 | $0 | $0 | ||||
| Total**** | $300 | $10 | $310 | ||||
**** Totals may not add up exactly to column amounts due to rounding
| Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (12/31/2025 b=c-a |
Current Approved (12/31/2025 c |
Cost to Date** (12/31/2025 d |
Cost Forecast (12/31/2025 e |
Cost Variance f=c-e |
||
| Preliminary Engineering |
$150 | $0 | $150 | $48 | $48 | $102 | |
| Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
| Construction |
$150 | $10 | $160 | $321 | $321 | $-160 | |
| Total* | $300 | $10 | $310 | $369 | $369 | $-59 | |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
| Project Schedule Baseline Summary | ||||||
|---|---|---|---|---|---|---|
| (Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2025) c |
% Complete (12/31/2025) d |
Schedule Forecast (12/31/2025) e |
Schedule Variance (months) f=c-e |
|
Begin Strategy Phase
End Strategy Phase |
08/26/2005 02/16/2007 |
|
08/26/2005 02/16/2007 |
100 | 10/01/2005 11/01/2007 |
-1 -9 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
04/16/2007 12/18/2007 |
10/15/2009 |
04/16/2007 09/30/2010 |
100 | 10/01/2010 03/01/2013 |
-42 -29 |
|
Begin Right of Way Phase
End Right of Way Phase |
04/23/2007 04/01/2008 |
10/15/2009 |
04/23/2007 09/30/2010 |
0 | |
0 0 |
|
Begin Construction Phase
End Construction Phase |
10/01/2008 04/01/2009 |
10/15/2009 10/15/2009 |
10/01/2010 10/31/2011 |
100 | 05/01/2014 02/10/2015 |
-44 -40 |
|
Begin Closeout Phase
End Closeout Phase |
10/01/2009 |
10/15/2009 |
12/31/2011 |
100 | 12/30/2015 09/13/2018 |
-49 0 |
????????
No map available at this time.
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Bridge Seismically Retrofitted | N | |
| Bond Funding Cost | |
|---|---|
| Adopted: |
$17,205 |
| Current Approved: |
$17,205 |
| Actual Expenditures: |
$17,205 |
Status as of December 31, 2025.
