Caltrans Logo

Bridge No. 53C0471 - WASHINGTON BLVD & RIO HONDO

Description: Bridge No. 53C0471 - WASHINGTON BLVD & RIO HONDO - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles County
City Montebello, Pico Rivera
Zip Code 90660
 
Senate District
30
Assembly District 58
Congressional District 38
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  N    Y  
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Los Angeles County Allan Abramson (626) 458-3950   aabrams@dpw.lacounty.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$95 $-32 $62
Non-bond Funding
State/Federal*
$1,047 $-249 $798
Local**
$45 $0 $45
Private***
$0 $0 $0
 
Total**** $1,187 $-282 $905

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$361 $0 $361 $343 $343 $18
Right of Way
$0 $0 $0 $3 $3 $-3
Construction
$826 $-282 $544 $623 $623 $-79
 
Total* $1,187 $-282 $905 $969 $969 $-64

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
08/31/1995 

04/30/2001 
 

 
08/31/1995 

04/30/2001 
100  08/31/1995 

05/29/2001 


-1 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
05/30/2001 

09/06/2007 
 

 
05/30/2001 

09/06/2007 
100  05/30/2001 

09/06/2007 


Begin Right of Way Phase

End Right of Way Phase
01/18/2007 

02/07/2008 
 

 
01/18/2007 

02/07/2008 
100  09/17/2007 

04/25/2008 
-8 

-3 
Begin Construction Phase

End Construction Phase
06/03/2008 

06/30/2010 
10/15/2009 

10/15/2009 
07/03/2008 

12/30/2009 
100  07/03/2008 

12/01/2009 


Begin Closeout Phase

End Closeout Phase
10/30/2010 

 
 

 
10/30/2010 

 
100  11/15/2010 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted N Y

Bond Funding Cost
Adopted:
$94,722
Current Approved:
$62,400
Actual Expenditures:
$62,400

 

Status as of December 31, 2023.