Bridge No. 53C0471 - WASHINGTON BLVD & RIO HONDO |
Description: Bridge No. 53C0471 - WASHINGTON BLVD & RIO HONDO - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Los Angeles County |
City | Montebello, Pico Rivera |
Zip Code | 90660 |
Senate District |
30 |
Assembly District | 58 |
Congressional District | 38 |
Caltrans District |
07 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N | Y |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Los Angeles County | Allan Abramson | (626) 458-3950 | aabrams@dpw.lacounty.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$95 | $-32 | $62 | ||||
Non-bond Funding | |||||||
State/Federal* |
$1,047 | $-249 | $798 | ||||
Local** |
$45 | $0 | $45 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $1,187 | $-282 | $905 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$361 | $0 | $361 | $343 | $343 | $18 | |
Right of Way |
$0 | $0 | $0 | $3 | $3 | $-3 | |
Construction |
$826 | $-282 | $544 | $623 | $623 | $-79 | |
Total* | $1,187 | $-282 | $905 | $969 | $969 | $-64 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
08/31/1995 04/30/2001 |
|
08/31/1995 04/30/2001 |
100 | 08/31/1995 05/29/2001 |
0 -1 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
05/30/2001 09/06/2007 |
|
05/30/2001 09/06/2007 |
100 | 05/30/2001 09/06/2007 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
01/18/2007 02/07/2008 |
|
01/18/2007 02/07/2008 |
100 | 09/17/2007 04/25/2008 |
-8 -3 |
Begin Construction Phase
End Construction Phase |
06/03/2008 06/30/2010 |
10/15/2009 10/15/2009 |
07/03/2008 12/30/2009 |
100 | 07/03/2008 12/01/2009 |
0 1 |
Begin Closeout Phase
End Closeout Phase |
10/30/2010 |
|
10/30/2010 |
100 | 11/15/2010 |
0 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N | Y |
Bond Funding Cost | |
---|---|
Adopted: |
$94,722 |
Current Approved: |
$62,400 |
Actual Expenditures: |
$62,400 |
Status as of December 31, 2023.