Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Bridge No. 53C0471 - WASHINGTON BLVD & RIO HONDO |
|
Description: Bridge No. 53C0471 - WASHINGTON BLVD & RIO HONDO - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
| Project Location | |
|---|---|
| County |
Los Angeles County |
| City | Montebello, Pico Rivera |
| Zip Code | 90660 |
| Senate District |
30 |
| Assembly District | 58 |
| Congressional District | 38 |
| Caltrans District |
07 |
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Bridge Seismically Retrofitted | N | Y |
| Project Contacts | Agency | Contact Person | Telephone | |
|---|---|---|---|---|
| Seismic |
Los Angeles County | Allan Abramson | (626) 458-3950 | aabrams@dpw.lacounty.gov |
| Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (12/31/2025 b=c-a |
Current Approved (12/31/2025 c |
|||||
| Bond Funding | |||||||
| LBSRA |
$95 | $-32 | $62 | ||||
| Non-bond Funding | |||||||
| State/Federal* |
$1,047 | $-249 | $798 | ||||
| Local** |
$45 | $0 | $45 | ||||
| Private*** |
$0 | $0 | $0 | ||||
| Total**** | $1,187 | $-282 | $905 | ||||
**** Totals may not add up exactly to column amounts due to rounding
| Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (12/31/2025 b=c-a |
Current Approved (12/31/2025 c |
Cost to Date** (12/31/2025 d |
Cost Forecast (12/31/2025 e |
Cost Variance f=c-e |
||
| Preliminary Engineering |
$361 | $0 | $361 | $343 | $343 | $18 | |
| Right of Way |
$0 | $0 | $0 | $3 | $3 | $-3 | |
| Construction |
$826 | $-282 | $544 | $623 | $623 | $-79 | |
| Total* | $1,187 | $-282 | $905 | $969 | $969 | $-64 | |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
| Project Schedule Baseline Summary | ||||||
|---|---|---|---|---|---|---|
| (Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2025) c |
% Complete (12/31/2025) d |
Schedule Forecast (12/31/2025) e |
Schedule Variance (months) f=c-e |
|
Begin Strategy Phase
End Strategy Phase |
08/31/1995 04/30/2001 |
|
08/31/1995 04/30/2001 |
100 | 08/31/1995 05/29/2001 |
0 -1 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
05/30/2001 09/06/2007 |
|
05/30/2001 09/06/2007 |
100 | 05/30/2001 09/06/2007 |
0 0 |
|
Begin Right of Way Phase
End Right of Way Phase |
01/18/2007 02/07/2008 |
|
01/18/2007 02/07/2008 |
100 | 09/17/2007 04/25/2008 |
-8 -3 |
|
Begin Construction Phase
End Construction Phase |
06/03/2008 06/30/2010 |
10/15/2009 10/15/2009 |
07/03/2008 12/30/2009 |
100 | 07/03/2008 12/01/2009 |
0 1 |
|
Begin Closeout Phase
End Closeout Phase |
10/30/2010 |
|
10/30/2010 |
100 | 11/15/2010 |
0 0 |
????????
No map available at this time.
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Bridge Seismically Retrofitted | N | Y |
| Bond Funding Cost | |
|---|---|
| Adopted: |
$94,722 |
| Current Approved: |
$62,400 |
| Actual Expenditures: |
$62,400 |
Status as of December 31, 2025.
