Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Bridge No. 53C0592 - CHERRY AVE & UP RR |
|
Description: Bridge No. 53C0592 - CHERRY AVE & UP RR - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
| Project Location | |
|---|---|
| County |
Los Angeles County |
| City | Lakewood |
| Zip Code | 90712, 90805 |
| Senate District |
25, 27 |
| Assembly District | 55 |
| Congressional District | 37, 39 |
| Caltrans District |
07 |
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Bridge Seismically Retrofitted | N | Y |
| Project Contacts | Agency | Contact Person | Telephone | |
|---|---|---|---|---|
| Seismic |
Los Angeles County | Allan Abramson | (626) 458-3950 | aabrams@dpw.lacounty.gov |
| Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (12/31/2025 b=c-a |
Current Approved (12/31/2025 c |
|||||
| Bond Funding | |||||||
| LBSRA |
$10 | $-2 | $8 | ||||
| Non-bond Funding | |||||||
| State/Federal* |
$298 | $-18 | $280 | ||||
| Local** |
$29 | $0 | $29 | ||||
| Private*** |
$0 | $0 | $0 | ||||
| Total**** | $338 | $-21 | $317 | ||||
**** Totals may not add up exactly to column amounts due to rounding
| Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (12/31/2025 b=c-a |
Current Approved (12/31/2025 c |
Cost to Date** (12/31/2025 d |
Cost Forecast (12/31/2025 e |
Cost Variance f=c-e |
||
| Preliminary Engineering |
$249 | $0 | $249 | $239 | $239 | $10 | |
| Right of Way |
$0 | $0 | $0 | $1 | $1 | $-1 | |
| Construction |
$89 | $-21 | $68 | $119 | $119 | $-51 | |
| Total* | $338 | $-21 | $317 | $359 | $359 | $-42 | |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
| Project Schedule Baseline Summary | ||||||
|---|---|---|---|---|---|---|
| (Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2025) c |
% Complete (12/31/2025) d |
Schedule Forecast (12/31/2025) e |
Schedule Variance (months) f=c-e |
|
Begin Strategy Phase
End Strategy Phase |
04/21/1995 09/15/1997 |
|
04/21/1995 09/15/1997 |
100 | 04/21/1995 10/14/1997 |
0 -1 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
10/15/1997 01/29/2008 |
10/15/2009 |
10/15/1997 12/27/2007 |
100 | 10/15/1997 12/27/2007 |
0 0 |
|
Begin Right of Way Phase
End Right of Way Phase |
04/16/2008 04/29/2008 |
10/15/2009 |
04/16/2008 05/05/2008 |
100 | 01/17/2008 05/05/2008 |
3 0 |
|
Begin Construction Phase
End Construction Phase |
07/31/2008 12/30/2009 |
10/15/2009 10/15/2009 |
09/22/2008 09/09/2009 |
100 | 09/22/2008 09/29/2009 |
0 -1 |
|
Begin Closeout Phase
End Closeout Phase |
04/30/2010 |
|
04/30/2010 |
100 | 11/18/2010 |
-6 0 |
????????
No map available at this time.
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Bridge Seismically Retrofitted | N | Y |
| Bond Funding Cost | |
|---|---|
| Adopted: |
$10,190 |
| Current Approved: |
$7,833 |
| Actual Expenditures: |
$7,833 |
Status as of December 31, 2025.
