Bridge No. 53C0867 - SOTO ST & LOS ANGELES RIVER

Description: Bridge No. 53C0867 - SOTO ST & LOS ANGELES RIVER - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles County
City Vernon
Zip Code 90023
 
Senate District
22
Assembly District 46
Congressional District 34
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  Y    Y  
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Los Angeles County Allan Abramson (626) 458-3950   aabrams@dpw.lacounty.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$393 $-35 $358
Non-bond Funding
State/Federal*
$3,280 $-274 $3,006
Local**
$36 $0 $36
Private***
$0 $0 $0
 
Total**** $3,709 $-309 $3,400

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$282 $0 $282 $726 $726 $-444
Right of Way
$0 $0 $0 $14 $14 $-14
Construction
$3,428 $-309 $3,118 $3,131 $3,131 $-13
 
Total* $3,709 $-309 $3,400 $3,872 $3,872 $-472

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
02/07/1995 

06/22/1996 
 

 
02/07/1995 

06/22/1996 
100  02/07/1995 

07/21/1996 


-1 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/22/1996 

10/03/2007 
 

 
07/22/1996 

10/03/2007 
100  07/22/1996 

10/03/2007 


Begin Right of Way Phase

End Right of Way Phase
01/18/2007 

02/11/2008 
 

 
01/18/2007 

04/25/2008 
100  10/24/2007 

04/25/2008 
-9 

Begin Construction Phase

End Construction Phase
05/13/2008 

05/30/2011 
10/15/2009 

10/15/2009 
07/03/2008 

05/30/2011 
100  07/03/2008 

05/26/2011 


Begin Closeout Phase

End Closeout Phase
09/30/2011 

 
 

 
09/30/2011 

 
100  05/27/2011 

02/14/2012 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted Y Y

Bond Funding Cost
Adopted:
$393,139
Current Approved:
$357,666
Actual Expenditures:
$357,666

 

Status as of December 31, 2023.