Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Bridge No. 53C0867 - SOTO ST & LOS ANGELES RIVER |
|
Description: Bridge No. 53C0867 - SOTO ST & LOS ANGELES RIVER - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
| Project Location | |
|---|---|
| County |
Los Angeles County |
| City | Vernon |
| Zip Code | 90023 |
| Senate District |
22 |
| Assembly District | 46 |
| Congressional District | 34 |
| Caltrans District |
07 |
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Bridge Seismically Retrofitted | Y | Y |
| Project Contacts | Agency | Contact Person | Telephone | |
|---|---|---|---|---|
| Seismic |
Los Angeles County | Allan Abramson | (626) 458-3950 | aabrams@dpw.lacounty.gov |
| Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (12/31/2025 b=c-a |
Current Approved (12/31/2025 c |
|||||
| Bond Funding | |||||||
| LBSRA |
$393 | $-35 | $358 | ||||
| Non-bond Funding | |||||||
| State/Federal* |
$3,280 | $-274 | $3,006 | ||||
| Local** |
$36 | $0 | $36 | ||||
| Private*** |
$0 | $0 | $0 | ||||
| Total**** | $3,709 | $-309 | $3,400 | ||||
**** Totals may not add up exactly to column amounts due to rounding
| Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (12/31/2025 b=c-a |
Current Approved (12/31/2025 c |
Cost to Date** (12/31/2025 d |
Cost Forecast (12/31/2025 e |
Cost Variance f=c-e |
||
| Preliminary Engineering |
$282 | $0 | $282 | $726 | $726 | $-444 | |
| Right of Way |
$0 | $0 | $0 | $14 | $14 | $-14 | |
| Construction |
$3,428 | $-309 | $3,118 | $3,131 | $3,131 | $-13 | |
| Total* | $3,709 | $-309 | $3,400 | $3,872 | $3,872 | $-472 | |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
| Project Schedule Baseline Summary | ||||||
|---|---|---|---|---|---|---|
| (Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2025) c |
% Complete (12/31/2025) d |
Schedule Forecast (12/31/2025) e |
Schedule Variance (months) f=c-e |
|
Begin Strategy Phase
End Strategy Phase |
02/07/1995 06/22/1996 |
|
02/07/1995 06/22/1996 |
100 | 02/07/1995 07/21/1996 |
0 -1 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
07/22/1996 10/03/2007 |
|
07/22/1996 10/03/2007 |
100 | 07/22/1996 10/03/2007 |
0 0 |
|
Begin Right of Way Phase
End Right of Way Phase |
01/18/2007 02/11/2008 |
|
01/18/2007 04/25/2008 |
100 | 10/24/2007 04/25/2008 |
-9 0 |
|
Begin Construction Phase
End Construction Phase |
05/13/2008 05/30/2011 |
10/15/2009 10/15/2009 |
07/03/2008 05/30/2011 |
100 | 07/03/2008 05/26/2011 |
0 0 |
|
Begin Closeout Phase
End Closeout Phase |
09/30/2011 |
|
09/30/2011 |
100 | 05/27/2011 02/14/2012 |
4 0 |
????????
No map available at this time.
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Bridge Seismically Retrofitted | Y | Y |
| Bond Funding Cost | |
|---|---|
| Adopted: |
$393,139 |
| Current Approved: |
$357,666 |
| Actual Expenditures: |
$357,666 |
Status as of December 31, 2025.
