Bridge No. 53C1909 - AT & SF RR & HUNTINGTON DR UP

Description: Bridge No. 53C1909 - AT & SF RR & HUNTINGTON DR UP - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles County
City Arcadia
Zip Code 91006
 
Senate District
29
Assembly District 44
Congressional District 26
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  Y    Y  
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Los Angeles County Allan Abramson (626) 458-3950   aabrams@dpw.lacounty.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$28 $1 $29
Non-bond Funding
State/Federal*
$498 $5 $503
Local**
$54 $0 $54
Private***
$0 $0 $0
 
Total**** $581 $5 $586

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$333 $0 $333 $286 $286 $47
Right of Way
$0 $0 $0 $3 $3 $-3
Construction
$248 $5 $253 $458 $458 $-204
 
Total* $581 $5 $586 $747 $747 $-160

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
04/21/1995 

04/30/2001 
 

 
04/21/1995 

04/30/2001 
100  04/21/1995 

05/29/2001 


-1 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
05/30/2001 

05/01/2007 
 

 
05/30/2001 

05/01/2007 
100  05/30/2001 

05/01/2007 


Begin Right of Way Phase

End Right of Way Phase
02/12/2008 

02/26/2008 
 

 
02/12/2008 

02/04/2009 
100  04/08/2008 

02/04/2009 
-2 

Begin Construction Phase

End Construction Phase
05/28/2008 

11/30/2009 
10/15/2009 

10/15/2009 
09/15/2009 

02/28/2013 
100  09/15/2009 

08/04/2011 


19 
Begin Closeout Phase

End Closeout Phase
03/30/2010 

 
10/15/2009 

 
03/01/2013 

 
100  08/05/2011 

05/29/2012 
19 

????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted Y Y

Bond Funding Cost
Adopted:
$28,460
Current Approved:
$29,067
Actual Expenditures:
$29,067

 

Status as of December 31, 2023.