Bridge No. 53C1909 - AT & SF RR & HUNTINGTON DR UP |
Description: Bridge No. 53C1909 - AT & SF RR & HUNTINGTON DR UP - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Los Angeles County |
City | Arcadia |
Zip Code | 91006 |
Senate District |
29 |
Assembly District | 44 |
Congressional District | 26 |
Caltrans District |
07 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y | Y |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Los Angeles County | Allan Abramson | (626) 458-3950 | aabrams@dpw.lacounty.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$28 | $1 | $29 | ||||
Non-bond Funding | |||||||
State/Federal* |
$498 | $5 | $503 | ||||
Local** |
$54 | $0 | $54 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $581 | $5 | $586 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$333 | $0 | $333 | $286 | $286 | $47 | |
Right of Way |
$0 | $0 | $0 | $3 | $3 | $-3 | |
Construction |
$248 | $5 | $253 | $458 | $458 | $-204 | |
Total* | $581 | $5 | $586 | $747 | $747 | $-160 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
04/21/1995 04/30/2001 |
|
04/21/1995 04/30/2001 |
100 | 04/21/1995 05/29/2001 |
0 -1 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
05/30/2001 05/01/2007 |
|
05/30/2001 05/01/2007 |
100 | 05/30/2001 05/01/2007 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
02/12/2008 02/26/2008 |
|
02/12/2008 02/04/2009 |
100 | 04/08/2008 02/04/2009 |
-2 0 |
Begin Construction Phase
End Construction Phase |
05/28/2008 11/30/2009 |
10/15/2009 10/15/2009 |
09/15/2009 02/28/2013 |
100 | 09/15/2009 08/04/2011 |
0 19 |
Begin Closeout Phase
End Closeout Phase |
03/30/2010 |
10/15/2009 |
03/01/2013 |
100 | 08/05/2011 05/29/2012 |
19 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y | Y |
Bond Funding Cost | |
---|---|
Adopted: |
$28,460 |
Current Approved: |
$29,067 |
Actual Expenditures: |
$29,067 |
Status as of December 31, 2023.