Bridge No. 54C0101 - MT VERNON AVE & UP RR & AMTRAK |
Description: Bridge No. 54C0101 - MT VERNON AVE & UP RR & AMTRAK - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
Project Location | |
---|---|
County |
San Bernardino County |
City | Colton |
Zip Code | 92324 |
Senate District |
32 |
Assembly District | 62 |
Congressional District | 43 |
Caltrans District |
08 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Colton | Victor Ortiz | (909) 370-5065 | VOrtiz@coltonca.gov. |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$19 | $0 | $19 | ||||
Non-bond Funding | |||||||
State/Federal* |
$217 | $7,635 | $7,852 | ||||
Local** |
$17 | $1,000 | $1,017 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $254 | $8,635 | $8,888 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$84 | $1,216 | $1,300 | $2,512 | $2,946 | $-1,646 | |
Right of Way |
$0 | $150 | $150 | $146 | $478 | $-328 | |
Construction |
$169 | $7,269 | $7,438 | $0 | $16,783 | $-9,345 | |
Total* | $254 | $8,635 | $8,888 | $2,658 | $20,208 | $-11,319 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
01/29/1992 01/29/1993 |
|
01/29/1992 01/29/1993 |
100 | 01/29/1992 01/29/1993 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
01/01/2009 07/01/2009 |
|
02/23/2018 06/30/2019 |
100 | 01/01/2009 12/31/2018 |
111 6 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
07/01/2019 12/31/2020 |
77 | 06/30/2019 03/31/2024 |
0 -40 |
Begin Construction Phase
End Construction Phase |
08/30/2009 07/31/2010 |
|
01/15/2021 06/30/2023 |
0 | 04/01/2024 03/31/2026 |
-39 -33 |
Begin Closeout Phase
End Closeout Phase |
|
|
12/31/2023 |
0 | 04/01/2026 09/30/2026 |
0 -33 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.