Bridge No. 54C0101 - MT VERNON AVE & UP RR & AMTRAK

Description: Bridge No. 54C0101 - MT VERNON AVE & UP RR & AMTRAK - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
Project Location
County
San Bernardino County
City Colton
Zip Code 92324
 
Senate District
32
Assembly District 62
Congressional District 43
 
Caltrans District
08
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  N      
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Colton Victor Ortiz (909) 370-5065   VOrtiz@coltonca.gov.
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$19 $0 $19
Non-bond Funding
State/Federal*
$217 $7,635 $7,852
Local**
$17 $1,000 $1,017
Private***
$0 $0 $0
 
Total**** $254 $8,635 $8,888

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$84 $1,216 $1,300 $2,512 $2,946 $-1,646
Right of Way
$0 $150 $150 $146 $478 $-328
Construction
$169 $7,269 $7,438 $0 $16,783 $-9,345
 
Total* $254 $8,635 $8,888 $2,658 $20,208 $-11,319

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
01/29/1992 

01/29/1993 
 

 
01/29/1992 

01/29/1993 
100  01/29/1992 

01/29/1993 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/01/2009 

07/01/2009 
 

 
02/23/2018 

06/30/2019 
100  01/01/2009 

12/31/2018 
111 

Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
07/01/2019 

12/31/2020 
77  06/30/2019 

03/31/2024 


-40 
Begin Construction Phase

End Construction Phase
08/30/2009 

07/31/2010 
 

 
01/15/2021 

06/30/2023 
04/01/2024 

03/31/2026 
-39 

-33 
Begin Closeout Phase

End Closeout Phase
 

 
 

 
 

12/31/2023 
04/01/2026 

09/30/2026 


-33 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted N

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.