Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Bridge No. 54C0101 - MT VERNON AVE & UP RR & AMTRAK |
|
Description: Bridge No. 54C0101 - MT VERNON AVE & UP RR & AMTRAK - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
| Project Location | |
|---|---|
| County |
San Bernardino County |
| City | Colton |
| Zip Code | 92324 |
| Senate District |
32 |
| Assembly District | 62 |
| Congressional District | 43 |
| Caltrans District |
08 |
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Bridge Seismically Retrofitted | N | |
| Project Contacts | Agency | Contact Person | Telephone | |
|---|---|---|---|---|
| Seismic |
Colton | Victor Ortiz | (909) 370-5065 | vortiz@coltonca.gov |
| Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (12/31/2025 b=c-a |
Current Approved (12/31/2025 c |
|||||
| Bond Funding | |||||||
| LBSRA |
$19 | $162 | $181 | ||||
| Non-bond Funding | |||||||
| State/Federal* |
$217 | $21,105 | $21,322 | ||||
| Local** |
$17 | $2,564 | $2,581 | ||||
| Private*** |
$0 | $0 | $0 | ||||
| Total**** | $254 | $23,832 | $24,085 | ||||
**** Totals may not add up exactly to column amounts due to rounding
| Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (12/31/2025 b=c-a |
Current Approved (12/31/2025 c |
Cost to Date** (12/31/2025 d |
Cost Forecast (12/31/2025 e |
Cost Variance f=c-e |
||
| Preliminary Engineering |
$84 | $1,216 | $1,300 | $2,512 | $2,946 | $-1,646 | |
| Right of Way |
$0 | $1,498 | $1,498 | $1,382 | $1,667 | $-169 | |
| Construction |
$169 | $21,118 | $21,287 | $0 | $24,538 | $-3,251 | |
| Total* | $254 | $23,832 | $24,085 | $3,894 | $29,151 | $-5,066 | |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
| Project Schedule Baseline Summary | ||||||
|---|---|---|---|---|---|---|
| (Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2025) c |
% Complete (12/31/2025) d |
Schedule Forecast (12/31/2025) e |
Schedule Variance (months) f=c-e |
|
Begin Strategy Phase
End Strategy Phase |
01/29/1992 01/29/1993 |
|
01/29/1992 01/29/1993 |
100 | 01/29/1992 01/29/1993 |
0 0 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
01/01/2009 07/01/2009 |
|
02/23/2018 06/30/2019 |
100 | 01/01/2009 12/31/2018 |
111 6 |
|
Begin Right of Way Phase
End Right of Way Phase |
|
|
07/01/2019 12/31/2020 |
98 | 06/30/2019 01/31/2026 |
0 -62 |
|
Begin Construction Phase
End Construction Phase |
08/30/2009 07/31/2010 |
|
01/15/2021 06/30/2023 |
0 | 02/01/2026 06/30/2028 |
-61 -61 |
|
Begin Closeout Phase
End Closeout Phase |
|
|
12/31/2023 |
0 | 07/01/2028 12/30/2028 |
0 -61 |
????????
No map available at this time.
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Bridge Seismically Retrofitted | N | |
| Bond Funding Cost | |
|---|---|
| Adopted: |
|
| Current Approved: |
|
| Actual Expenditures: |
|
Status as of December 31, 2025.
