Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Bridge No. 54C0375 - WEST C ST & UP RR |
|
Description: Bridge No. 54C0375 - WEST C ST & UP RR - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
| Project Location | |
|---|---|
| County |
San Bernardino County |
| City | Colton |
| Zip Code | 92324 |
| Senate District |
32 |
| Assembly District | 62 |
| Congressional District | 43 |
| Caltrans District |
08 |
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Bridge Seismically Retrofitted | N | Y |
| Project Contacts | Agency | Contact Person | Telephone | |
|---|---|---|---|---|
| Seismic |
Colton | vortiz@ci.colton.ca.us | (909) 370-5065 | vortiz@ci.colton.ca.us |
| Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (12/31/2025 b=c-a |
Current Approved (12/31/2025 c |
|||||
| Bond Funding | |||||||
| LBSRA |
$15 | $0 | $15 | ||||
| Non-bond Funding | |||||||
| State/Federal* |
$155 | $0 | $155 | ||||
| Local** |
$5 | $0 | $5 | ||||
| Private*** |
$0 | $0 | $0 | ||||
| Total**** | $175 | $0 | $175 | ||||
**** Totals may not add up exactly to column amounts due to rounding
| Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (12/31/2025 b=c-a |
Current Approved (12/31/2025 c |
Cost to Date** (12/31/2025 d |
Cost Forecast (12/31/2025 e |
Cost Variance f=c-e |
||
| Preliminary Engineering |
$45 | $0 | $45 | $45 | $45 | $0 | |
| Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
| Construction |
$130 | $0 | $130 | $66 | $66 | $64 | |
| Total* | $175 | $0 | $175 | $111 | $111 | $64 | |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
| Project Schedule Baseline Summary | ||||||
|---|---|---|---|---|---|---|
| (Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2025) c |
% Complete (12/31/2025) d |
Schedule Forecast (12/31/2025) e |
Schedule Variance (months) f=c-e |
|
Begin Strategy Phase
End Strategy Phase |
03/25/1996 03/25/1997 |
|
03/25/1996 03/25/1997 |
100 | 03/25/1996 03/25/1997 |
0 0 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
01/01/2009 07/01/2009 |
|
01/01/2009 07/01/2009 |
100 | 01/01/2009 03/31/2014 |
0 -58 |
|
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
100 | 07/01/2014 08/28/2014 |
0 0 |
|
Begin Construction Phase
End Construction Phase |
08/30/2009 07/31/2010 |
|
08/30/2009 07/31/2010 |
100 | 11/01/2016 06/30/2017 |
-87 -84 |
|
Begin Closeout Phase
End Closeout Phase |
06/30/2010 |
|
06/30/2010 |
100 | 07/01/2017 07/31/2019 |
-85 0 |
????????
No map available at this time.
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Bridge Seismically Retrofitted | N | Y |
| Bond Funding Cost | |
|---|---|
| Adopted: |
$14,911 |
| Current Approved: |
$14,911 |
| Actual Expenditures: |
$7,559 |
Status as of December 31, 2025.
