Bridge No. 55C0151 - BAYSIDE DR & GOLDENROD AVE POC |
Description: Bridge No. 55C0151 - BAYSIDE DR & GOLDENROD AVE POC - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Orange County |
City | Newport Beach |
Zip Code | 92625 |
Senate District |
35 |
Assembly District | 70 |
Congressional District | 48 |
Caltrans District |
12 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y | Y |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Newport Beach | fong tse | 949-644-3321 | ftse@newportbeachca.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$46 | $-28 | $18 | ||||
Non-bond Funding | |||||||
State/Federal* |
$288 | $-61 | $227 | ||||
Local** |
$20 | $22 | $41 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $353 | $-67 | $286 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$0 | $109 | $109 | $109 | $109 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$353 | $-176 | $177 | $157 | $157 | $20 | |
Total* | $353 | $-67 | $286 | $266 | $266 | $20 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
01/01/2003 06/18/2003 |
|
01/01/2003 06/18/2003 |
100 | 01/01/2003 06/18/2003 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
06/19/2003 03/31/2008 |
|
06/19/2003 10/02/2009 |
100 | 05/02/2002 10/02/2009 |
14 0 |
Begin Right of Way Phase
End Right of Way Phase |
12/01/2007 03/31/2008 |
|
11/21/2008 05/05/2009 |
100 | 11/21/2008 05/05/2009 |
0 0 |
Begin Construction Phase
End Construction Phase |
09/01/2008 03/01/2009 |
|
11/15/2010 05/31/2011 |
100 | 11/15/2010 05/31/2011 |
0 0 |
Begin Closeout Phase
End Closeout Phase |
06/30/2009 |
|
06/30/2009 |
50 | 11/30/2011 05/15/2012 |
-29 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y | Y |
Bond Funding Cost | |
---|---|
Adopted: |
$45,880 |
Current Approved: |
$151,404 |
Actual Expenditures: |
$123,953 |
Status as of December 31, 2023.