Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Bridge No. 55C0151 - BAYSIDE DR & GOLDENROD AVE POC |
|
Description: Bridge No. 55C0151 - BAYSIDE DR & GOLDENROD AVE POC - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
| Project Location | |
|---|---|
| County |
Orange County |
| City | Newport Beach |
| Zip Code | 92625 |
| Senate District |
35 |
| Assembly District | 70 |
| Congressional District | 48 |
| Caltrans District |
12 |
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Bridge Seismically Retrofitted | Y | Y |
| Project Contacts | Agency | Contact Person | Telephone | |
|---|---|---|---|---|
| Seismic |
Newport Beach | fong tse | 949-644-3321 | ftse@newportbeachca.gov |
| Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (12/31/2025 b=c-a |
Current Approved (12/31/2025 c |
|||||
| Bond Funding | |||||||
| LBSRA |
$46 | $-28 | $18 | ||||
| Non-bond Funding | |||||||
| State/Federal* |
$288 | $-61 | $227 | ||||
| Local** |
$20 | $22 | $41 | ||||
| Private*** |
$0 | $0 | $0 | ||||
| Total**** | $353 | $-67 | $286 | ||||
**** Totals may not add up exactly to column amounts due to rounding
| Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (12/31/2025 b=c-a |
Current Approved (12/31/2025 c |
Cost to Date** (12/31/2025 d |
Cost Forecast (12/31/2025 e |
Cost Variance f=c-e |
||
| Preliminary Engineering |
$0 | $109 | $109 | $109 | $109 | $0 | |
| Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
| Construction |
$353 | $-176 | $177 | $157 | $157 | $20 | |
| Total* | $353 | $-67 | $286 | $266 | $266 | $20 | |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
| Project Schedule Baseline Summary | ||||||
|---|---|---|---|---|---|---|
| (Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2025) c |
% Complete (12/31/2025) d |
Schedule Forecast (12/31/2025) e |
Schedule Variance (months) f=c-e |
|
Begin Strategy Phase
End Strategy Phase |
01/01/2003 06/18/2003 |
|
01/01/2003 06/18/2003 |
100 | 01/01/2003 06/18/2003 |
0 0 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
06/19/2003 03/31/2008 |
|
06/19/2003 10/02/2009 |
100 | 05/02/2002 10/02/2009 |
14 0 |
|
Begin Right of Way Phase
End Right of Way Phase |
12/01/2007 03/31/2008 |
|
11/21/2008 05/05/2009 |
100 | 11/21/2008 05/05/2009 |
0 0 |
|
Begin Construction Phase
End Construction Phase |
09/01/2008 03/01/2009 |
|
11/15/2010 05/31/2011 |
100 | 11/15/2010 05/31/2011 |
0 0 |
|
Begin Closeout Phase
End Closeout Phase |
06/30/2009 |
|
06/30/2009 |
50 | 11/30/2011 05/15/2012 |
-29 0 |
????????
No map available at this time.
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Bridge Seismically Retrofitted | Y | Y |
| Bond Funding Cost | |
|---|---|
| Adopted: |
$45,880 |
| Current Approved: |
$151,404 |
| Actual Expenditures: |
$123,953 |
Status as of December 31, 2025.
