Bridge No. 57C0398 - CARLTON OAKS DR & SYCAMORE CREEK

Description: Bridge No. 57C0398 - CARLTON OAKS DR & SYCAMORE CREEK - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Diego County
City Santee
Zip Code 92071
 
Senate District
36
Assembly District 77
Congressional District 52
 
Caltrans District
11
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  N      
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Santee Carl Schmitz (619) 258-4100   cschmitz@cityofsanteeca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$21 $0 $21
Non-bond Funding
State/Federal*
$159 $-71 $88
Local**
$20 $0 $20
Private***
$0 $0 $0
 
Total**** $200 $-71 $129

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$20 $88 $108 $79 $100 $8
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$180 $-159 $21 $0 $400 $-379
 
Total* $200 $-71 $129 $79 $500 $-371

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
09/30/2008 

12/30/2008 
 

 
09/30/2008 

12/30/2008 
100  09/30/2008 

03/20/2012 


-39 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
03/30/2009 

08/30/2009 
 

10/15/2009 
03/30/2009 

04/01/2011 
60  02/04/2013 

12/31/2017 
-47 

-82 
Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
02/28/2010 

10/30/2010 
10/15/2009 

10/15/2009 
06/01/2011 

11/30/2011 
01/31/2018 

05/31/2018 
-81 

-79 
Begin Closeout Phase

End Closeout Phase
04/30/2011 

 
 

 
04/30/2011 

 
07/01/2018 

08/31/2018 
-87 

????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted N

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.