Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Bridge No. 57C0398 - CARLTON OAKS DR & SYCAMORE CREEK |
Description: Bridge No. 57C0398 - CARLTON OAKS DR & SYCAMORE CREEK - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Diego County |
City | Santee |
Zip Code | 92071 |
Senate District |
36 |
Assembly District | 77 |
Congressional District | 52 |
Caltrans District |
11 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Santee | Carl Schmitz | (619) 258-4100 | cschmitz@cityofsanteeca.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$21 | $0 | $21 | ||||
Non-bond Funding | |||||||
State/Federal* |
$159 | $-71 | $88 | ||||
Local** |
$20 | $0 | $20 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $200 | $-71 | $129 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$20 | $88 | $108 | $79 | $100 | $8 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$180 | $-159 | $21 | $0 | $400 | $-379 | |
Total* | $200 | $-71 | $129 | $79 | $500 | $-371 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
09/30/2008 12/30/2008 |
|
09/30/2008 12/30/2008 |
100 | 09/30/2008 03/20/2012 |
0 -39 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
03/30/2009 08/30/2009 |
10/15/2009 |
03/30/2009 04/01/2011 |
60 | 02/04/2013 12/31/2017 |
-47 -82 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
02/28/2010 10/30/2010 |
10/15/2009 10/15/2009 |
06/01/2011 11/30/2011 |
0 | 01/31/2018 05/31/2018 |
-81 -79 |
Begin Closeout Phase
End Closeout Phase |
04/30/2011 |
|
04/30/2011 |
0 | 07/01/2018 08/31/2018 |
-87 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.