Bridge No. 57C0398 - CARLTON OAKS DR & SYCAMORE CREEK |
|
Description: Bridge No. 57C0398 - CARLTON OAKS DR & SYCAMORE CREEK - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
| Project Location | |
|---|---|
| County |
San Diego County |
| City | Santee |
| Zip Code | 92071 |
| Senate District |
36 |
| Assembly District | 77 |
| Congressional District | 52 |
| Caltrans District |
11 |
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Bridge Seismically Retrofitted | N | |
| Project Contacts | Agency | Contact Person | Telephone | |
|---|---|---|---|---|
| Seismic |
Santee | Carl Schmitz | (619) 258-4100 | cschmitz@cityofsanteeca.gov |
| Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (12/31/2025 b=c-a |
Current Approved (12/31/2025 c |
|||||
| Bond Funding | |||||||
| LBSRA |
$21 | $0 | $21 | ||||
| Non-bond Funding | |||||||
| State/Federal* |
$159 | $-71 | $88 | ||||
| Local** |
$20 | $0 | $20 | ||||
| Private*** |
$0 | $0 | $0 | ||||
| Total**** | $200 | $-71 | $129 | ||||
**** Totals may not add up exactly to column amounts due to rounding
| Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (12/31/2025 b=c-a |
Current Approved (12/31/2025 c |
Cost to Date** (12/31/2025 d |
Cost Forecast (12/31/2025 e |
Cost Variance f=c-e |
||
| Preliminary Engineering |
$20 | $88 | $108 | $79 | $100 | $8 | |
| Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
| Construction |
$180 | $-159 | $21 | $0 | $400 | $-379 | |
| Total* | $200 | $-71 | $129 | $79 | $500 | $-371 | |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
| Project Schedule Baseline Summary | ||||||
|---|---|---|---|---|---|---|
| (Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2025) c |
% Complete (12/31/2025) d |
Schedule Forecast (12/31/2025) e |
Schedule Variance (months) f=c-e |
|
Begin Strategy Phase
End Strategy Phase |
09/30/2008 12/30/2008 |
|
09/30/2008 12/30/2008 |
100 | 09/30/2008 03/20/2012 |
0 -39 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
03/30/2009 08/30/2009 |
10/15/2009 |
03/30/2009 04/01/2011 |
60 | 02/04/2013 12/31/2017 |
-47 -82 |
|
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
|
Begin Construction Phase
End Construction Phase |
02/28/2010 10/30/2010 |
10/15/2009 10/15/2009 |
06/01/2011 11/30/2011 |
0 | 01/31/2018 05/31/2018 |
-81 -79 |
|
Begin Closeout Phase
End Closeout Phase |
04/30/2011 |
|
04/30/2011 |
0 | 07/01/2018 08/31/2018 |
-87 0 |
????????
No map available at this time.
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Bridge Seismically Retrofitted | N | |
| Bond Funding Cost | |
|---|---|
| Adopted: |
|
| Current Approved: |
|
| Actual Expenditures: |
|
Status as of December 31, 2025.