Caltrans Logo

Tehachapi Trade Corridor Project

Description: Rail Capacity Improvement

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Kern
City Tehachapi
Zip Code
 
Senate District
18
Assembly District 32
Congressional District 22
 
Caltrans District
06
 
 
County/State Route Kern 58
Postmile Begin/End
Project Benefits
 Benefit Baseline Actual
Additional Track Miles Layed  2.8      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Caltrans / BNSF Bruce Roberts (916) 654-7293   bruce_roberts@dot.ca.gov
Design (PS&E) Phase
Caltrans / BNSF Bruce Roberts (916) 654-7293   bruce_roberts@dot.ca.gov
Right of Way Phase
Caltrans / BNSF Bruce Roberts (916) 654-7293   bruce_roberts@dot.ca.gov
Construction Phase
Caltrans / BNSF Bruce Roberts (916) 654-7293   bruce_roberts@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TCIF
$54,000 $-41,730 $12,270
Non-bond Funding
State/Federal*
$1,500 $0 $1,500
Local**
$57,200 $-57,200 $0
Private***
$0 $12,270 $12,270
 
Total**** $112,700 $-86,660 $26,040

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$3,700 $5,800 $9,500 $9,500 $9,500 $0
Design(PS&E)
$1,000 $0 $1,000 $1,000 $1,000 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$108,000 $-92,460 $15,540 $15,540 $15,540 $0
 
Total* $112,700 $-86,660 $26,040 $26,040 $26,040 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
01/01/2008 

06/01/2010 
05/07/2013 

05/07/2013 
09/01/2008 

10/01/2013 
100   

06/03/2014 


-8 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/01/2008 

12/01/2011 
 

05/07/2013 
01/01/2008 

09/01/2013 
100   

08/31/2013 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
03/01/2012 

10/01/2014 
05/07/2013 

05/07/2013 
09/24/2014 

10/01/2016 
100  09/01/2014 

05/31/2017 


-8 
Begin Closeout Phase

End Closeout Phase
01/01/2015 

12/01/2015 
05/07/2013 

 
10/01/2016 

03/31/2017 
100  05/31/2017 

04/30/2018 
-8 

-13 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Additional Track Miles Layed 2.8

Bond Funding Cost
Adopted:
$54,000,000
Current Approved:
$12,270,000
Actual Expenditures:
$12,270,000

 

Status as of December 31, 2023.