South Milliken Avenue Grade Separation at Union Pacific Los Angeles Subdivision

Description: Construct Grade Separation

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Bernardino
City Ontario
Zip Code 91764
 
Senate District
31, 32
Assembly District 61, 71
Congressional District 43, 44
 
Caltrans District
08
 
Project Benefits
 Benefit Baseline Actual
Rail/Highway At-Grade Crossings Eliminated  1    1  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
City of Ontario Jay Bautista (909) 395-2120   jbautista@ontarioca.gov
Design (PS&E) Phase
City of Ontario Jay Bautista (909) 395-2120   jbautista@ontarioca.gov
Right of Way Phase
City of Ontario Jay Bautista (909) 395-2120   jbautista@ontarioca.gov
Construction Phase
City of Ontario Jay Bautista (909) 395-2120   jbautista@ontarioca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TCIF
$8,031 $12,602 $20,633
SLPP
$0 $7,210 $7,210
Non-bond Funding
State/Federal*
$0 $0 $0
Local**
$68,084 $-35,699 $32,385
Private***
$0 $2,482 $2,482
 
Total**** $76,115 $-13,405 $62,710

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$750 $0 $750 $678 $678 $72
Design(PS&E)
$2,000 $2,745 $4,745 $5,652 $5,652 $-907
Right of Way
$3,736 $1,485 $5,221 $14,490 $14,490 $-9,269
Construction
$69,629 $-17,635 $51,994 $51,897 $51,897 $97
 
Total* $76,115 $-13,405 $62,710 $72,718 $72,718 $-10,008

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
07/01/2008 

12/31/2009 
 

01/08/2013 
07/01/2008 

06/25/2010 
100  07/01/2008 

06/25/2010 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/01/2010 

12/31/2011 
06/30/2010 

01/08/2013 
06/16/2010 

03/07/2013 
100  06/16/2010 

03/07/2013 


Begin Right of Way Phase

End Right of Way Phase
01/01/2010 

06/30/2012 
01/08/2013 

06/11/2013 
07/01/2011 

06/05/2013 
100  07/01/2011 

06/05/2013 


Begin Construction Phase

End Construction Phase
12/01/2012 

12/31/2014 
06/11/2013 

06/11/2013 
12/11/2013 

06/01/2016 
100  12/03/2013 

11/21/2017 


-18 
Begin Closeout Phase

End Closeout Phase
01/01/2015 

04/30/2015 
06/11/2013 

 
07/01/2016 

02/01/2017 
75  11/21/2017 

08/10/2023 
-17 

-79 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Rail/Highway At-Grade Crossings Eliminated 1 1

Bond Funding Cost
Adopted:
$8,031,000
Current Approved:
$20,633,000
Actual Expenditures:
$20,535,712

 

Status as of December 31, 2023.