Redwood Road

Description: Redwood Road

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Alameda County
City
Zip Code 94544
 
Senate District
10
Assembly District 20
Congressional District 09
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Peak Delay Time Saving(minutes)  0      
Peak Period Time Savings (minutes)      1.0  
 
Project Contacts Agency Contact Person Telephone E-mail
TLSP
Alameda County Paul Keener (510) 670-6452   paulk@acpwa.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TLSP
$124 $-3 $121
Non-bond Funding
State/Federal*
$0 $0 $0
Local**
$35 $0 $35
Private***
$0 $0 $0
 
Total**** $159 $-3 $156

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$25 $0 $25 $25 $25 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$134 $-3 $131 $131 $131 $0
 
Total* $159 $-3 $156 $156 $156 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
08/30/2008 

09/30/2008 
 

 
08/30/2008 

09/30/2008 
100  08/30/2008 

09/30/2008 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
09/30/2008 

10/30/2008 
 

 
09/30/2008 

10/30/2008 
100  09/30/2008 

01/26/2010 


-15 
Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
02/28/2009 

04/30/2009 
09/22/2010 

09/22/2010 
03/16/2010 

09/30/2010 
100  03/16/2010 

09/30/2010 


Begin Closeout Phase

End Closeout Phase
06/30/2009 

07/30/2009 
09/22/2010 

 
10/01/2010 

12/31/2010 
100  10/01/2010 

12/01/2010 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Peak Delay Time Saving(minutes) 0
Peak Period Time Savings (minutes) 1.0

Bond Funding Cost
Adopted:
$124,000
Current Approved:
$121,000
Actual Expenditures:
$120,542

 

Status as of December 31, 2023.