San Pablo Corridor |
Description: San Pablo Corridor
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Alameda County |
City | |
Zip Code | 94544 |
Senate District |
07, 09 |
Assembly District | 11, 14, 16 |
Congressional District | 07, 09 |
Caltrans District |
04 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Peak Delay Time Saving(minutes) | 30940 | |
Peak Period Time Savings (minutes) | 30940 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
TLSP |
Alameda CountyTransportation Commission | Vivek Bhat | (510) 208-7430 | vbhat@alamedactc.org |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
TLSP |
$21,400 | $-2,685 | $18,715 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $0 | $0 | ||||
Local** |
$6,900 | $0 | $6,900 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $28,300 | $-2,685 | $25,615 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$300 | $0 | $300 | $300 | $300 | $0 | |
Design(PS&E) |
$2,600 | $0 | $2,600 | $2,600 | $2,600 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$25,400 | $-2,685 | $22,715 | $18,715 | $18,715 | $4,001 | |
Total* | $28,300 | $-2,685 | $25,615 | $21,615 | $21,615 | $4,001 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
08/01/2008 04/02/2009 |
|
08/01/2008 04/02/2009 |
100 | 07/02/2007 09/28/2009 |
13 -6 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
10/01/2008 08/12/2009 |
01/19/2011 |
10/01/2008 01/01/2010 |
100 | 10/01/2008 09/01/2010 |
0 -8 |
Begin Right of Way Phase
End Right of Way Phase |
04/02/2009 08/21/2009 |
|
04/02/2009 08/21/2009 |
100 | 04/30/2009 09/01/2010 |
-1 -13 |
Begin Construction Phase
End Construction Phase |
12/04/2009 11/26/2010 |
01/19/2011 01/19/2011 |
01/01/2011 10/13/2013 |
100 | 04/18/2011 12/31/2019 |
-4 -76 |
Begin Closeout Phase
End Closeout Phase |
04/02/2012 10/01/2012 |
01/19/2011 |
10/31/2013 10/31/2014 |
0 | 12/31/2019 03/31/2020 |
-75 -66 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Peak Delay Time Saving(minutes) | 30940 | |
Peak Period Time Savings (minutes) | 30940 |
Bond Funding Cost | |
---|---|
Adopted: |
$21,400,000 |
Current Approved: |
$18,715,405 |
Actual Expenditures: |
$18,714,760 |
Status as of December 31, 2023.