San Pablo Corridor

Description: San Pablo Corridor

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Alameda County
City
Zip Code 94544
 
Senate District
07, 09
Assembly District 11, 14, 16
Congressional District 07, 09
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Peak Delay Time Saving(minutes)  30940      
Peak Period Time Savings (minutes)      30940  
 
Project Contacts Agency Contact Person Telephone E-mail
TLSP
Alameda CountyTransportation Commission Vivek Bhat (510) 208-7430   vbhat@alamedactc.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TLSP
$21,400 $-2,685 $18,715
Non-bond Funding
State/Federal*
$0 $0 $0
Local**
$6,900 $0 $6,900
Private***
$0 $0 $0
 
Total**** $28,300 $-2,685 $25,615

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$300 $0 $300 $300 $300 $0
Design(PS&E)
$2,600 $0 $2,600 $2,600 $2,600 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$25,400 $-2,685 $22,715 $18,715 $18,715 $4,001
 
Total* $28,300 $-2,685 $25,615 $21,615 $21,615 $4,001

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
08/01/2008 

04/02/2009 
 

 
08/01/2008 

04/02/2009 
100  07/02/2007 

09/28/2009 
13 

-6 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
10/01/2008 

08/12/2009 
 

01/19/2011 
10/01/2008 

01/01/2010 
100  10/01/2008 

09/01/2010 


-8 
Begin Right of Way Phase

End Right of Way Phase
04/02/2009 

08/21/2009 
 

 
04/02/2009 

08/21/2009 
100  04/30/2009 

09/01/2010 
-1 

-13 
Begin Construction Phase

End Construction Phase
12/04/2009 

11/26/2010 
01/19/2011 

01/19/2011 
01/01/2011 

10/13/2013 
100  04/18/2011 

12/31/2019 
-4 

-76 
Begin Closeout Phase

End Closeout Phase
04/02/2012 

10/01/2012 
01/19/2011 

 
10/31/2013 

10/31/2014 
12/31/2019 

03/31/2020 
-75 

-66 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Peak Delay Time Saving(minutes) 30940
Peak Period Time Savings (minutes) 30940

Bond Funding Cost
Adopted:
$21,400,000
Current Approved:
$18,715,405
Actual Expenditures:
$18,714,760

 

Status as of December 31, 2023.