TLSP Phase II Greenback Lane

Description: TLSP Phase II Greenback Lane

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Sacramento County
City Citrus Heights
Zip Code 95610, 95621
 
Senate District
06
Assembly District 05
Congressional District 03
 
Caltrans District
03
 
Project Benefits
 Benefit Baseline Actual
Peak Delay Time Saving(minutes)  3912      
Peak Period Time Savings (minutes)      20%  
 
Project Contacts Agency Contact Person Telephone E-mail
TLSP
Citrus Heights Stuart Hodgkins (916) 727-4770   shodgkins@citrusheights.net
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TLSP
$180 $0 $180
Non-bond Funding
State/Federal*
$20 $0 $20
Local**
$38 $0 $38
Private***
$0 $0 $0
 
Total**** $238 $0 $238

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$2 $0 $2 $2 $2 $0
Design(PS&E)
$18 $0 $18 $18 $18 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$218 $0 $218 $218 $218 $0
 
Total* $238 $0 $238 $238 $238 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
05/30/2008 

06/30/2008 
 

 
05/30/2008 

06/30/2008 
100  05/30/2008 

06/30/2008 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
02/01/2007 

05/30/2008 
 

 
02/01/2007 

05/30/2008 
100  02/01/2007 

05/30/2008 


Begin Right of Way Phase

End Right of Way Phase
05/30/2008 

05/30/2008 
 

 
05/30/2008 

05/30/2008 
100  05/30/2008 

05/30/2008 


Begin Construction Phase

End Construction Phase
07/31/2008 

11/30/2008 
 

 
07/31/2008 

11/30/2008 
100  12/29/2008 

04/30/2010 
-5 

-17 
Begin Closeout Phase

End Closeout Phase
12/30/2008 

12/30/2008 
 

 
12/30/2008 

12/30/2008 
100  03/15/2010 

10/30/2010 
-15 

-22 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Peak Delay Time Saving(minutes) 3912
Peak Period Time Savings (minutes) 20%

Bond Funding Cost
Adopted:
$180,000
Current Approved:
$180,000
Actual Expenditures:
$180,000

 

Status as of December 31, 2023.