TLSP Phase III Antelope Road

Description: TLSP Phase III Antelope Road

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Sacramento County
City Citrus Heights
Zip Code 95610, 95621
 
Senate District
06
Assembly District 05
Congressional District 03
 
Caltrans District
03
 
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)      20%  
Peak Delay Time Saving(minutes)  1600      
 
Project Contacts Agency Contact Person Telephone E-mail
TLSP
Citrus Heights Stuart Hodgkins (916) 727-4771   shodgkins@citrusheights.net
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TLSP
$102 $0 $102
Non-bond Funding
State/Federal*
$0 $0 $0
Local**
$29 $-7 $22
Private***
$0 $0 $0
 
Total**** $131 $-7 $124

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$2 $-2 $0 $2 $2 $-2
Design(PS&E)
$5 $-5 $0 $5 $5 $-5
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$124 $0 $124 $125 $125 $-1
 
Total* $131 $-7 $124 $132 $132 $-8

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
08/30/2009 

09/30/2009 
 

 
08/30/2009 

09/30/2009 
100  08/30/2009 

01/30/2010 


-4 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
11/30/2009 

11/30/2009 
 

 
11/30/2009 

11/30/2009 
100  03/30/2010 

05/30/2010 
-4 

-6 
Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
06/01/2010 

06/01/2010 


Begin Construction Phase

End Construction Phase
01/30/2010 

04/30/2010 
09/22/2010 

09/22/2010 
09/23/2010 

04/30/2011 
100  06/01/2010 

09/30/2011 


-5 
Begin Closeout Phase

End Closeout Phase
05/30/2010 

05/30/2010 
09/22/2010 

 
05/01/2011 

06/30/2011 
100  11/01/2011 

02/29/2012 
-6 

-8 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 20%
Peak Delay Time Saving(minutes) 1600

Bond Funding Cost
Adopted:
$102,000
Current Approved:
$102,000
Actual Expenditures:
$102,000

 

Status as of December 31, 2023.