TLSP Phase III Antelope Road |
Description: TLSP Phase III Antelope Road
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Sacramento County |
City | Citrus Heights |
Zip Code | 95610, 95621 |
Senate District |
06 |
Assembly District | 05 |
Congressional District | 03 |
Caltrans District |
03 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 20% | |
Peak Delay Time Saving(minutes) | 1600 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
TLSP |
Citrus Heights | Stuart Hodgkins | (916) 727-4771 | shodgkins@citrusheights.net |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
TLSP |
$102 | $0 | $102 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $0 | $0 | ||||
Local** |
$29 | $-7 | $22 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $131 | $-7 | $124 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$2 | $-2 | $0 | $2 | $2 | $-2 | |
Design(PS&E) |
$5 | $-5 | $0 | $5 | $5 | $-5 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$124 | $0 | $124 | $125 | $125 | $-1 | |
Total* | $131 | $-7 | $124 | $132 | $132 | $-8 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
08/30/2009 09/30/2009 |
|
08/30/2009 09/30/2009 |
100 | 08/30/2009 01/30/2010 |
0 -4 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
11/30/2009 11/30/2009 |
|
11/30/2009 11/30/2009 |
100 | 03/30/2010 05/30/2010 |
-4 -6 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | 06/01/2010 06/01/2010 |
0 0 |
Begin Construction Phase
End Construction Phase |
01/30/2010 04/30/2010 |
09/22/2010 09/22/2010 |
09/23/2010 04/30/2011 |
100 | 06/01/2010 09/30/2011 |
4 -5 |
Begin Closeout Phase
End Closeout Phase |
05/30/2010 05/30/2010 |
09/22/2010 |
05/01/2011 06/30/2011 |
100 | 11/01/2011 02/29/2012 |
-6 -8 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 20% | |
Peak Delay Time Saving(minutes) | 1600 |
Bond Funding Cost | |
---|---|
Adopted: |
$102,000 |
Current Approved: |
$102,000 |
Actual Expenditures: |
$102,000 |
Status as of December 31, 2023.