Caltrans Logo

Rosecrans Ave.

Description: Rosecrans Ave.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles County
City Compton
Zip Code 90220
 
Senate District
25
Assembly District 52, 55
Congressional District 37
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Peak Delay Time Saving(minutes)  16605      
 
Project Contacts Agency Contact Person Telephone E-mail
TLSP
Compton John D. Strickland Jr (310) 761-1422   jstrickland@comptoncity.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TLSP
$1,050 $-367 $683
Non-bond Funding
State/Federal*
$0 $0 $0
Local**
$402 $-141 $261
Private***
$0 $0 $0
 
Total**** $1,452 $-508 $944

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$86 $-86 $0 $0 $0 $0
Construction
$1,366 $-422 $944 $944 $944 $0
 
Total* $1,452 $-508 $944 $944 $944 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
01/10/2007 

10/14/2008 
 

 
01/10/2007 

10/14/2008 
100  01/10/2007 

10/14/2008 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
04/30/2008 

04/30/2008 
 

 
04/30/2007 

04/30/2008 
100  04/30/2008 

03/03/2009 
-12 

-10 
Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
01/30/2009 

01/30/2010 
03/23/2011 

06/27/2012 
02/01/2011 

10/01/2012 
100  11/29/2010 

06/30/2016 


-46 
Begin Closeout Phase

End Closeout Phase
01/30/2010 

01/30/2010 
06/27/2012 

 
04/30/2013 

10/30/2013 
50  08/06/2018 

10/01/2018 
-64 

-60 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Peak Delay Time Saving(minutes) 16605

Bond Funding Cost
Adopted:
$1,050,000
Current Approved:
$682,734
Actual Expenditures:
$682,734

 

Status as of December 31, 2023.