TLSP ATMS Phase II |
Description: TLSP ATMS Phase II
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Riverside County |
City | Corona |
Zip Code | 92878, 92880, 92881, 92882 |
Senate District |
37 |
Assembly District | 71 |
Congressional District | 44 |
Caltrans District |
08 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Peak Delay Time Saving(minutes) | 40316 | |
Peak Period Time Savings (minutes) | 20% |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
TLSP |
Corona | Albert Espinoza | (951) 279-3548 | albert.espinoza@ci.corona.ca.us |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
TLSP |
$4,488 | $0 | $4,488 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $0 | $0 | ||||
Local** |
$1,023 | $0 | $1,023 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $5,511 | $0 | $5,511 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$5,511 | $0 | $5,511 | $5,510 | $5,510 | $1 | |
Total* | $5,511 | $0 | $5,511 | $5,510 | $5,510 | $1 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
|
|
0 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
09/30/2008 12/30/2008 |
|
09/30/2008 12/30/2008 |
100 | 12/01/2008 04/30/2009 |
-2 -4 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
06/01/2009 06/01/2010 |
05/05/2011 05/05/2011 |
06/01/2009 09/01/2011 |
100 | 08/05/2009 09/01/2011 |
-2 0 |
Begin Closeout Phase
End Closeout Phase |
06/30/2010 09/30/2010 |
05/11/2011 |
09/30/2011 12/31/2011 |
100 | 09/30/2011 12/31/2011 |
0 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Peak Delay Time Saving(minutes) | 40316 | |
Peak Period Time Savings (minutes) | 20% |
Bond Funding Cost | |
---|---|
Adopted: |
$4,488,000 |
Current Approved: |
$4,487,493 |
Actual Expenditures: |
$4,487,493 |
Status as of December 31, 2023.