Citywide TLSP

Description: Citywide TLSP

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles County
City Culver City
Zip Code 90066, 90230, 90232
 
Senate District
26
Assembly District 47
Congressional District 33
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)      36%  
Peak Delay Time Saving(minutes)  25604      
 
Project Contacts Agency Contact Person Telephone E-mail
TLSP
Culver City Mate Gaspar (310) 253-5602   mate.gaspar@culvercity.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TLSP
$440 $-241 $199
Non-bond Funding
State/Federal*
$0 $0 $0
Local**
$110 $-60 $50
Private***
$0 $0 $0
 
Total**** $550 $-301 $249

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$550 $-301 $249 $249 $249 $0
 
Total* $550 $-301 $249 $249 $249 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
09/28/2008 

09/28/2008 
 

 
09/28/2008 

09/28/2008 
100  04/01/2009 

04/01/2009 
-6 

-6 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
11/26/2008 

11/26/2008 
06/01/2009 

06/01/2009 
04/14/2009 

09/01/2009 
100  03/01/2010 

06/30/2010 
-11 

-10 
Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
12/27/2008 

01/29/2009 
03/23/2011 

03/23/2011 
04/01/2010 

05/02/2011 
100  07/01/2010 

03/31/2011 
-3 

Begin Closeout Phase

End Closeout Phase
04/28/2009 

06/27/2009 
03/23/2011 

 
06/10/2011 

07/11/2011 
100  04/01/2011 

12/31/2011 


-6 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 36%
Peak Delay Time Saving(minutes) 25604

Bond Funding Cost
Adopted:
$440,000
Current Approved:
$199,224
Actual Expenditures:
$199,224

 

Status as of December 31, 2023.