Clovis Avenue

Description: Clovis Avenue

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Fresno County
City Fresno
Zip Code 93721
 
Senate District
14, 16
Assembly District 29, 31
Congressional District 21
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)      27.7%  
Peak Delay Time Saving(minutes)  33448      
Peak Period Time Savings (minutes)      42,713  
 
Project Contacts Agency Contact Person Telephone E-mail
TLSP
Fresno John Stanboulian (559) 621-8669   john.stanboulian@fresno.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TLSP
$2,100 $-141 $1,959
Non-bond Funding
State/Federal*
$1,119 $0 $1,119
Local**
$52 $0 $52
Private***
$0 $0 $0
 
Total**** $3,271 $-141 $3,130

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$183 $0 $183 $231 $231 $-47
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$3,087 $-141 $2,946 $2,884 $2,884 $63
 
Total* $3,271 $-141 $3,130 $3,114 $3,114 $15

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/01/2008 

03/31/2009 
 

05/25/2009 
07/01/2008 

10/31/2009 
100  07/01/2008 

10/31/2009 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
06/15/2009 

05/31/2010 
09/22/2010 

09/22/2010 
02/08/2011 

10/31/2011 
100  09/23/2010 

03/26/2012 


-5 
Begin Closeout Phase

End Closeout Phase
06/01/2010 

09/30/2010 
09/22/2010 

 
11/01/2011 

04/30/2012 
100  04/01/2012 

02/15/2015 
-5 

-34 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 27.7%
Peak Delay Time Saving(minutes) 33448
Peak Period Time Savings (minutes) 42,713

Bond Funding Cost
Adopted:
$2,100,000
Current Approved:
$1,959,000
Actual Expenditures:
$1,958,569

 

Status as of December 31, 2023.