Caltrans Logo

Shaw Avenue

Description: Shaw Avenue

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Fresno County
City Fresno
Zip Code 93721
 
Senate District
14, 16
Assembly District 29
Congressional District 19, 21
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Peak Delay Time Saving(minutes)  77215      
Peak Period Time Savings (minutes)      77215  
 
Project Contacts Agency Contact Person Telephone E-mail
TLSP
Fresno John Stanboulian (559) 621-8669   john.stanboulian@fresno.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TLSP
$2,100 $-413 $1,687
Non-bond Funding
State/Federal*
$1,023 $0 $1,023
Local**
$42 $0 $42
Private***
$0 $0 $0
 
Total**** $3,166 $-413 $2,753

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$163 $0 $163 $248 $248 $-85
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$3,003 $-413 $2,590 $2,475 $2,475 $115
 
Total* $3,166 $-413 $2,753 $2,723 $2,723 $30

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/01/2008 

03/31/2009 
 

09/22/2010 
07/01/2008 

02/28/2011 
100  07/01/2008 

03/30/2012 


-13 
Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
06/15/2009 

05/31/2010 
03/28/2012 

03/28/2012 
09/30/2012 

06/30/2013 
100  09/30/2012 

04/10/2014 


-9 
Begin Closeout Phase

End Closeout Phase
06/01/2010 

09/30/2010 
04/10/2012 

 
09/30/2013 

12/31/2013 
100  04/01/2015 

09/30/2016 
-18 

-33 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Peak Delay Time Saving(minutes) 77215
Peak Period Time Savings (minutes) 77215

Bond Funding Cost
Adopted:
$2,100,000
Current Approved:
$1,687,000
Actual Expenditures:
$1,686,289

 

Status as of December 31, 2023.