TMC Upgrade |
Description: TMC Upgrade
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Orange County |
City | Garden Grove |
Zip Code | 92840, 92841, 92842 |
Senate District |
34, 35 |
Assembly District | 67, 68, 69 |
Congressional District | 45, 46 |
Caltrans District |
12 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 0% | |
Peak Delay Time Saving(minutes) | 18975 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
TLSP |
Garden Grove | Ana Neal | (714) 741-5176 | anan@ci.garden-grove.ca.us |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
TLSP |
$1,859 | $0 | $1,859 | ||||
Non-bond Funding | |||||||
State/Federal* |
$1,683 | $0 | $1,683 | ||||
Local** |
$1,216 | $-1 | $1,216 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $4,758 | $-0 | $4,758 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$305 | $-0 | $304 | $702 | $702 | $-398 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$4,454 | $0 | $4,454 | $4,154 | $4,154 | $300 | |
Total* | $4,758 | $-0 | $4,758 | $4,856 | $4,856 | $-98 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
07/01/2008 07/01/2008 |
|
07/01/2008 07/01/2008 |
100 | 05/01/2008 05/01/2008 |
2 2 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
08/01/2008 09/01/2008 |
|
08/01/2008 09/01/2008 |
100 | 07/20/2005 05/14/2010 |
37 -21 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
01/01/2009 04/01/2009 |
01/19/2011 09/14/2011 |
06/01/2010 11/30/2011 |
100 | 02/25/2008 03/30/2012 |
28 -4 |
Begin Closeout Phase
End Closeout Phase |
05/01/2009 06/01/2009 |
10/31/2012 |
12/01/2011 06/29/2012 |
100 | 04/02/2012 06/29/2012 |
-4 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 0% | |
Peak Delay Time Saving(minutes) | 18975 |
Bond Funding Cost | |
---|---|
Adopted: |
$1,858,720 |
Current Approved: |
$1,859,000 |
Actual Expenditures: |
$1,859,000 |
Status as of December 31, 2023.