Description: Brand Blvd.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Los Angeles County |
City | Glendale |
Zip Code | 91206 |
Senate District |
22 |
Assembly District | 43 |
Congressional District | 29 |
Caltrans District |
07 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Peak Delay Time Saving(minutes) | 7207 | |
Peak Period Time Savings (minutes) | 8,403 | 8,403 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
TLSP |
Glendale | Fred Zohrehvand | (818) 937-8328 | fzohrehvand@ci.glendale.ca.us |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
TLSP |
$930 | $-123 | $807 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $0 | $0 | ||||
Local** |
$451 | $-0 | $451 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $1,381 | $-123 | $1,258 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$219 | $0 | $219 | $0 | $0 | $219 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$1,162 | $-123 | $1,039 | $1,031 | $1,031 | $8 | |
Total* | $1,381 | $-123 | $1,258 | $1,031 | $1,031 | $227 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
11/10/2008 11/15/2008 |
|
11/10/2008 11/15/2008 |
100 | 01/12/2009 02/10/2009 |
-2 -3 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
02/10/2009 05/04/2009 |
06/22/2011 06/22/2011 |
02/09/2010 06/30/2011 |
100 | 04/09/2010 06/30/2011 |
-2 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
06/08/2009 12/04/2009 |
03/28/2012 03/28/2012 |
07/01/2012 03/31/2013 |
100 | 01/01/2013 04/14/2014 |
-6 -13 |
Begin Closeout Phase
End Closeout Phase |
12/18/2009 12/30/2009 |
03/28/2012 |
04/04/2013 06/03/2013 |
100 | 12/30/2015 01/30/2017 |
-33 -45 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Peak Delay Time Saving(minutes) | 7207 | |
Peak Period Time Savings (minutes) | 8,403 | 8,403 |
Bond Funding Cost | |
---|---|
Adopted: |
$930,000 |
Current Approved: |
$807,000 |
Actual Expenditures: |
$807,925 |
Status as of December 31, 2023.