Caltrans Logo

Glendale Ave./ Verdugo Rd

Description: Glendale Ave./ Verdugo Rd

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles County
City Glendale
Zip Code 91206
 
Senate District
22
Assembly District 43
Congressional District 29
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Peak Delay Time Saving(minutes)  8778      
Peak Period Time Savings (minutes)  10,665    10,665  
 
Project Contacts Agency Contact Person Telephone E-mail
TLSP
Glendale Fred Zohrehvand (818) 937-8328   fzohrehvand@ci.glendale.ca.us
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TLSP
$1,798 $-390 $1,408
Non-bond Funding
State/Federal*
$0 $0 $0
Local**
$873 $0 $873
Private***
$0 $0 $0
 
Total**** $2,671 $-390 $2,281

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$423 $0 $423 $0 $0 $423
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$2,248 $-390 $1,858 $1,794 $1,794 $64
 
Total* $2,671 $-390 $2,281 $1,794 $1,794 $487

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
11/10/2008 

11/15/2008 
 

 
11/10/2008 

11/15/2008 
100  01/12/2009 

02/10/2009 
-2 

-3 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
02/10/2009 

05/04/2009 
06/22/2011 

06/22/2011 
02/09/2010 

06/30/2011 
100  02/10/2010 

06/30/2011 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
06/08/2009 

12/04/2009 
03/28/2012 

03/28/2012 
07/01/2012 

03/31/2013 
100  08/01/2012 

06/14/2014 
-1 

-15 
Begin Closeout Phase

End Closeout Phase
12/18/2009 

12/30/2009 
03/28/2012 

 
04/04/2013 

06/03/2013 
100  01/30/2017 

01/30/2017 
-47 

-45 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Peak Delay Time Saving(minutes) 8778
Peak Period Time Savings (minutes) 10,665 10,665

Bond Funding Cost
Adopted:
$1,798,000
Current Approved:
$1,408,000
Actual Expenditures:
$1,407,460

 

Status as of December 31, 2023.