12th Avenue

Description: 12th Avenue

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Kings County
City Hanford
Zip Code 93230
 
Senate District
16
Assembly District 30
Congressional District 20
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Peak Delay Time Saving(minutes)  2670      
Peak Period Time Savings (minutes)      30%  
 
Project Contacts Agency Contact Person Telephone E-mail
TLSP
Hanford John Doyel (559) 585-2571   jdoyel@ci.hanford.ca.us
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TLSP
$90 $-19 $71
Non-bond Funding
State/Federal*
$40 $0 $40
Local**
$75 $-18 $57
Private***
$0 $0 $0
 
Total**** $205 $-37 $168

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$45 $-4 $41 $45 $45 $-4
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$160 $-33 $127 $121 $121 $6
 
Total* $205 $-37 $168 $166 $166 $3

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
07/28/2008 

08/15/2008 
 

10/14/2009 
07/28/2008 

04/30/2009 
100  07/30/2008 

04/30/2009 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/30/2009 

03/30/2009 
 

10/14/2009 
01/30/2009 

11/15/2009 
100  01/30/2009 

04/01/2010 


-5 
Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
10/30/2008 

12/31/2008 
10/14/2009 

10/14/2009 
12/01/2009 

02/28/2010 
100  05/01/2010 

12/31/2010 
-5 

-10 
Begin Closeout Phase

End Closeout Phase
01/31/2009 

02/28/2009 
10/14/2009 

 
03/15/2010 

04/15/2010 
100  02/15/2011 

02/12/2015 
-11 

-59 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Peak Delay Time Saving(minutes) 2670
Peak Period Time Savings (minutes) 30%

Bond Funding Cost
Adopted:
$90,000
Current Approved:
$71,126
Actual Expenditures:
$70,430

 

Status as of December 31, 2023.