La Brea Avenue

Description: La Brea Avenue

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles County
City Inglewood
Zip Code 90312
 
Senate District
25
Assembly District 51
Congressional District 35
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Peak Delay Time Saving(minutes)  5400      
Peak Period Time Savings (minutes)      5400  
 
Project Contacts Agency Contact Person Telephone E-mail
TLSP
Inglewood Alan Mai (310) 412-5333   amai@cityofinglewood.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TLSP
$426 $-37 $389
Non-bond Funding
State/Federal*
$0 $0 $0
Local**
$180 $0 $180
Private***
$0 $0 $0
 
Total**** $606 $-37 $569

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$606 $-37 $569 $576 $576 $-7
 
Total* $606 $-37 $569 $576 $576 $-7

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
07/30/2007 

10/30/2007 
 

 
07/30/2007 

10/30/2007 
100  06/05/2008 

01/03/2012 
-10 

-51 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
11/30/2007 

07/30/2008 
 

 
11/30/2007 

07/30/2008 
100  02/10/2014 

10/20/2014 
-75 

-76 
Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
12/30/2008 

09/30/2009 
05/23/2012 

05/23/2012 
08/01/2013 

01/31/2014 
100  05/28/2015 

05/05/2016 
-22 

-27 
Begin Closeout Phase

End Closeout Phase
10/30/2009 

12/30/2009 
05/23/2012 

 
05/30/2014 

08/29/2014 
100  03/03/2017 

09/12/2017 
-34 

-37 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Peak Delay Time Saving(minutes) 5400
Peak Period Time Savings (minutes) 5400

Bond Funding Cost
Adopted:
$426,000
Current Approved:
$389,000
Actual Expenditures:
$388,228

 

Status as of December 31, 2023.