ATCS - Central Business District |
Description: ATCS - Central Business District
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Los Angeles County |
City | Los Angeles |
Zip Code | 90012 |
Senate District |
22 |
Assembly District | 46 |
Congressional District | 34 |
Caltrans District |
07 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Peak Delay Time Saving(minutes) | 67620 | |
Peak Period Time Savings (minutes) | 67620 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
TLSP |
Los Angeles | Bill Shao | (213) 972-8668 | bill.shao@lacity.org |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
TLSP |
$748 | $-748 | $0 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $0 | $0 | ||||
Local** |
$8,467 | $0 | $8,467 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $9,215 | $-748 | $8,467 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$1,106 | $0 | $1,106 | $1,106 | $1,106 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$8,109 | $-748 | $7,361 | $5,690 | $5,690 | $1,671 | |
Total* | $9,215 | $-748 | $8,467 | $6,796 | $6,796 | $1,671 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
01/17/2008 01/17/2008 |
|
01/17/2008 01/17/2008 |
100 | 11/03/2008 11/25/2008 |
-9 -10 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
01/30/2010 10/30/2010 |
08/19/2013 08/19/2013 |
06/01/2014 09/01/2016 |
100 | 07/01/2015 08/01/2016 |
-13 1 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
01/30/2011 02/28/2014 |
10/19/2016 10/19/2016 |
12/01/2016 03/01/2018 |
100 | 05/10/2017 02/12/2019 |
-5 -12 |
Begin Closeout Phase
End Closeout Phase |
02/28/2014 08/30/2014 |
10/19/2016 |
09/30/2018 03/31/2019 |
100 | 02/12/2019 02/27/2019 |
-4 1 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Peak Delay Time Saving(minutes) | 67620 | |
Peak Period Time Savings (minutes) | 67620 |
Bond Funding Cost | |
---|---|
Adopted: |
$748,000 |
Current Approved: |
$0 |
Actual Expenditures: |
$0 |
Status as of December 31, 2023.