ATCS - Central Business District

Description: ATCS - Central Business District

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles County
City Los Angeles
Zip Code 90012
 
Senate District
22
Assembly District 46
Congressional District 34
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Peak Delay Time Saving(minutes)  67620      
Peak Period Time Savings (minutes)      67620  
 
Project Contacts Agency Contact Person Telephone E-mail
TLSP
Los Angeles Bill Shao (213) 972-8668   bill.shao@lacity.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TLSP
$748 $-748 $0
Non-bond Funding
State/Federal*
$0 $0 $0
Local**
$8,467 $0 $8,467
Private***
$0 $0 $0
 
Total**** $9,215 $-748 $8,467

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$1,106 $0 $1,106 $1,106 $1,106 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$8,109 $-748 $7,361 $5,690 $5,690 $1,671
 
Total* $9,215 $-748 $8,467 $6,796 $6,796 $1,671

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
01/17/2008 

01/17/2008 
 

 
01/17/2008 

01/17/2008 
100  11/03/2008 

11/25/2008 
-9 

-10 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/30/2010 

10/30/2010 
08/19/2013 

08/19/2013 
06/01/2014 

09/01/2016 
100  07/01/2015 

08/01/2016 
-13 

Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
01/30/2011 

02/28/2014 
10/19/2016 

10/19/2016 
12/01/2016 

03/01/2018 
100  05/10/2017 

02/12/2019 
-5 

-12 
Begin Closeout Phase

End Closeout Phase
02/28/2014 

08/30/2014 
10/19/2016 

 
09/30/2018 

03/31/2019 
100  02/12/2019 

02/27/2019 
-4 

????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Peak Delay Time Saving(minutes) 67620
Peak Period Time Savings (minutes) 67620

Bond Funding Cost
Adopted:
$748,000
Current Approved:
$0
Actual Expenditures:
$0

 

Status as of December 31, 2023.