Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
ATCS - Central City East |
Description: ATCS - Central City East
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Los Angeles County |
City | Los Angeles |
Zip Code | 90012 |
Senate District |
22 |
Assembly District | 45, 46 |
Congressional District | 34 |
Caltrans District |
07 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Peak Delay Time Saving(minutes) | 0 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
TLSP |
Los Angeles | Bill Shao | (213) 972-8668 | bill.shao@lacity.org |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
TLSP |
$0 | $0 | $0 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $0 | $0 | ||||
Local** |
$4,885 | $0 | $4,885 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $4,885 | $0 | $4,885 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$586 | $0 | $586 | $586 | $586 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$4,299 | $0 | $4,299 | $3,908 | $3,908 | $391 | |
Total* | $4,885 | $0 | $4,885 | $4,494 | $4,494 | $391 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
01/17/2008 01/17/2008 |
|
01/17/2008 01/17/2008 |
100 | 11/03/2008 11/25/2008 |
-9 -10 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
07/30/2010 01/30/2011 |
08/19/2013 10/19/2016 |
12/01/2014 07/01/2016 |
100 | 03/01/2015 03/01/2016 |
-3 4 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
04/30/2011 05/30/2014 |
10/19/2016 10/19/2016 |
08/01/2016 08/01/2017 |
100 | 08/10/2016 02/12/2019 |
0 -19 |
Begin Closeout Phase
End Closeout Phase |
05/30/2014 11/30/2014 |
10/19/2016 |
02/28/2018 08/31/2018 |
100 | 02/12/2019 02/27/2019 |
-12 -6 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Peak Delay Time Saving(minutes) | 0 |
Bond Funding Cost | |
---|---|
Adopted: |
$0 |
Current Approved: |
$0 |
Actual Expenditures: |
$0 |
Status as of December 31, 2023.