Description: ATCS - Central City East

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles County
City Los Angeles
Zip Code 90012
 
Senate District
22
Assembly District 45, 46
Congressional District 34
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Peak Delay Time Saving(minutes)  0      
 
Project Contacts Agency Contact Person Telephone E-mail
TLSP
Los Angeles Bill Shao (213) 972-8668   bill.shao@lacity.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TLSP
$0 $0 $0
Non-bond Funding
State/Federal*
$0 $0 $0
Local**
$4,885 $0 $4,885
Private***
$0 $0 $0
 
Total**** $4,885 $0 $4,885

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$586 $0 $586 $586 $586 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$4,299 $0 $4,299 $3,908 $3,908 $391
 
Total* $4,885 $0 $4,885 $4,494 $4,494 $391

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
01/17/2008 

01/17/2008 
 

 
01/17/2008 

01/17/2008 
100  11/03/2008 

11/25/2008 
-9 

-10 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/30/2010 

01/30/2011 
08/19/2013 

10/19/2016 
12/01/2014 

07/01/2016 
100  03/01/2015 

03/01/2016 
-3 

Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
04/30/2011 

05/30/2014 
10/19/2016 

10/19/2016 
08/01/2016 

08/01/2017 
100  08/10/2016 

02/12/2019 


-19 
Begin Closeout Phase

End Closeout Phase
05/30/2014 

11/30/2014 
10/19/2016 

 
02/28/2018 

08/31/2018 
100  02/12/2019 

02/27/2019 
-12 

-6 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Peak Delay Time Saving(minutes) 0

Bond Funding Cost
Adopted:
$0
Current Approved:
$0
Actual Expenditures:
$0

 

Status as of December 31, 2023.