Caltrans Logo

ATCS - Los Angeles

Description: ATCS - Los Angeles

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles County
City Los Angeles
Zip Code 90012
 
Senate District
17, 20, 21, 22, 23, 24, 25, 26, 27, 28, 29, 30
Assembly District 37, 38, 39, 40, 41, 42, 43, 44, 45, 46, 47, 48, 51, 52, 53, 54, 55
Congressional District 25, 27, 28, 29, 30, 31, 32, 33, 34, 35, 36, 37, 39, 46
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Peak Delay Time Saving(minutes)  49072      
Peak Period Time Savings (minutes)      49072  
 
Project Contacts Agency Contact Person Telephone E-mail
TLSP
Los Angeles Bill Shao (213) 972-8668   bill.shao@lacity.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TLSP
$26,748 $-18,860 $7,888
Non-bond Funding
State/Federal*
$0 $0 $0
Local**
$3,815 $1 $3,816
Private***
$0 $0 $0
 
Total**** $30,563 $-18,859 $11,704

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$3,815 $1 $3,816 $3,816 $3,816 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$26,748 $-18,860 $7,888 $7,888 $7,888 $0
 
Total* $30,563 $-18,859 $11,704 $11,704 $11,704 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
01/17/2008 

01/17/2008 
 

 
01/17/2008 

01/17/2008 
100  11/03/2008 

11/25/2008 
-9 

-10 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/30/2009 

07/30/2010 
08/19/2013 

08/19/2013 
07/01/2013 

07/01/2014 
100  03/01/2014 

11/30/2016 
-8 

-29 
Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
10/30/2010 

10/30/2014 
08/19/2013 

08/19/2013 
11/01/2014 

05/01/2016 
100  08/08/2017 

06/28/2019 
-34 

-38 
Begin Closeout Phase

End Closeout Phase
10/30/2014 

04/30/2015 
 

 
05/01/2016 

11/01/2016 
100  06/28/2019 

06/30/2019 
-38 

-32 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Peak Delay Time Saving(minutes) 49072
Peak Period Time Savings (minutes) 49072

Bond Funding Cost
Adopted:
$26,748,000
Current Approved:
$7,888,072
Actual Expenditures:
$7,888,072

 

Status as of December 31, 2023.