ATCS - Westwood / West Los Angeles

Description: ATCS - Westwood / West Los Angeles

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles County
City Los Angeles
Zip Code 90012
 
Senate District
23, 26, 28
Assembly District 42, 47, 53
Congressional District 30, 36
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Peak Delay Time Saving(minutes)  29400      
Peak Period Time Savings (minutes)      29400  
 
Project Contacts Agency Contact Person Telephone E-mail
TLSP
Los Angeles Bill Shao (213) 972-8668   bill.shao@lacity.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TLSP
$3,850 $-1,221 $2,629
Non-bond Funding
State/Federal*
$0 $0 $0
Local**
$525 $0 $525
Private***
$0 $0 $0
 
Total**** $4,375 $-1,221 $3,154

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$525 $0 $525 $525 $525 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$3,850 $-1,221 $2,629 $2,629 $2,629 $0
 
Total* $4,375 $-1,221 $3,154 $3,154 $3,154 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
01/17/2008 

01/17/2008 
 

 
01/17/2008 

01/17/2008 
100  11/03/2008 

11/25/2008 
-9 

-10 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
10/30/2009 

03/30/2010 
01/19/2011 

01/19/2011 
06/01/2011 

10/01/2011 
100  07/01/2011 

04/05/2012 
-1 

-6 
Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
06/30/2010 

07/30/2013 
01/19/2011 

01/19/2011 
01/01/2012 

02/01/2015 
100  04/03/2013 

10/16/2014 
-15 

Begin Closeout Phase

End Closeout Phase
07/30/2013 

01/30/2014 
01/19/2011 

 
02/01/2015 

08/01/2015 
100  10/16/2014 

12/01/2017 


-28 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Peak Delay Time Saving(minutes) 29400
Peak Period Time Savings (minutes) 29400

Bond Funding Cost
Adopted:
$3,850,000
Current Approved:
$2,629,200
Actual Expenditures:
$2,628,800

 

Status as of December 31, 2023.