ATCS - Westwood / West Los Angeles |
Description: ATCS - Westwood / West Los Angeles
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Los Angeles County |
City | Los Angeles |
Zip Code | 90012 |
Senate District |
23, 26, 28 |
Assembly District | 42, 47, 53 |
Congressional District | 30, 36 |
Caltrans District |
07 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Peak Delay Time Saving(minutes) | 29400 | |
Peak Period Time Savings (minutes) | 29400 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
TLSP |
Los Angeles | Bill Shao | (213) 972-8668 | bill.shao@lacity.org |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
TLSP |
$3,850 | $-1,221 | $2,629 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $0 | $0 | ||||
Local** |
$525 | $0 | $525 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $4,375 | $-1,221 | $3,154 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$525 | $0 | $525 | $525 | $525 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$3,850 | $-1,221 | $2,629 | $2,629 | $2,629 | $0 | |
Total* | $4,375 | $-1,221 | $3,154 | $3,154 | $3,154 | $0 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
01/17/2008 01/17/2008 |
|
01/17/2008 01/17/2008 |
100 | 11/03/2008 11/25/2008 |
-9 -10 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
10/30/2009 03/30/2010 |
01/19/2011 01/19/2011 |
06/01/2011 10/01/2011 |
100 | 07/01/2011 04/05/2012 |
-1 -6 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
06/30/2010 07/30/2013 |
01/19/2011 01/19/2011 |
01/01/2012 02/01/2015 |
100 | 04/03/2013 10/16/2014 |
-15 4 |
Begin Closeout Phase
End Closeout Phase |
07/30/2013 01/30/2014 |
01/19/2011 |
02/01/2015 08/01/2015 |
100 | 10/16/2014 12/01/2017 |
4 -28 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Peak Delay Time Saving(minutes) | 29400 | |
Peak Period Time Savings (minutes) | 29400 |
Bond Funding Cost | |
---|---|
Adopted: |
$3,850,000 |
Current Approved: |
$2,629,200 |
Actual Expenditures: |
$2,628,800 |
Status as of December 31, 2023.