ATCS - Wilshire East

Description: ATCS - Wilshire East

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles County
City Los Angeles
Zip Code 90012
 
Senate District
22, 26
Assembly District 46, 48
Congressional District 31, 34
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Peak Delay Time Saving(minutes)  41160      
Peak Period Time Savings (minutes)      41160  
 
Project Contacts Agency Contact Person Telephone E-mail
TLSP
Los Angeles Bill Shao (213) 972-8668   bill.shao@lacity.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TLSP
$5,276 $-927 $4,349
Non-bond Funding
State/Federal*
$0 $0 $0
Local**
$720 $435 $1,155
Private***
$0 $0 $0
 
Total**** $5,996 $-492 $5,504

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$720 $-1 $719 $719 $719 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$5,276 $-491 $4,785 $4,785 $4,785 $0
 
Total* $5,996 $-492 $5,504 $5,504 $5,504 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
01/17/2008 

01/17/2008 
 

 
01/17/2008 

01/17/2008 
100  01/17/2008 

01/17/2008 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
11/30/2009 

06/30/2010 
08/19/2013 

08/19/2013 
08/01/2013 

01/01/2014 
100  08/01/2013 

03/01/2014 


-2 
Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
09/30/2010 

10/30/2013 
08/19/2013 

08/19/2013 
05/01/2014 

05/01/2015 
100  12/10/2014 

07/25/2016 
-7 

-15 
Begin Closeout Phase

End Closeout Phase
10/30/2013 

04/30/2014 
01/19/2011 

 
08/01/2015 

02/01/2016 
100  07/25/2016 

03/09/2018 
-12 

-26 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Peak Delay Time Saving(minutes) 41160
Peak Period Time Savings (minutes) 41160

Bond Funding Cost
Adopted:
$5,276,000
Current Approved:
$4,349,179
Actual Expenditures:
$4,349,179

 

Status as of December 31, 2023.