Caltrans Logo

ATSAC - Platt Ranch

Description: ATSAC - Platt Ranch

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles County
City Los Angeles
Zip Code 90012
 
Senate District
17, 23
Assembly District 37, 40
Congressional District 30
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)      0%  
Peak Delay Time Saving(minutes)  33408      
 
Project Contacts Agency Contact Person Telephone E-mail
TLSP
Los Angeles Verej Janoyan (213) 972-5050   verej.janoyan@lacity.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TLSP
$4,358 $1 $4,359
Non-bond Funding
State/Federal*
$0 $0 $0
Local**
$547 $0 $547
Private***
$0 $0 $0
 
Total**** $4,905 $1 $4,906

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$547 $0 $547 $547 $547 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$4,358 $1 $4,359 $4,358 $4,358 $1
 
Total* $4,905 $1 $4,906 $4,905 $4,905 $1

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
01/17/2008 

01/17/2008 
 

 
01/17/2008 

01/17/2008 
100  11/03/2008 

11/25/2008 
-9 

-10 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
06/30/2008 

12/30/2008 
 

 
06/30/2008 

12/30/2008 
100  06/02/2008 

12/01/2008 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
03/30/2009 

04/30/2012 
07/09/2009 

07/09/2009 
12/01/2009 

01/01/2013 
100  11/19/2009 

12/19/2012 


Begin Closeout Phase

End Closeout Phase
04/30/2012 

10/30/2012 
 

 
01/01/2013 

07/01/2013 
100  12/19/2012 

06/19/2013 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 0%
Peak Delay Time Saving(minutes) 33408

Bond Funding Cost
Adopted:
$4,358,000
Current Approved:
$4,358,600
Actual Expenditures:
$4,358,000

 

Status as of December 31, 2023.