ATSAC - Reseda Phase 2

Description: ATSAC - Reseda Phase 2

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles County
City Los Angeles
Zip Code 90012
 
Senate District
17, 20, 21
Assembly District 38, 40
Congressional District 27, 30
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Peak Delay Time Saving(minutes)  64512      
Peak Period Time Savings (minutes)      1-13%  
 
Project Contacts Agency Contact Person Telephone E-mail
TLSP
Los Angeles Verej Janoyan (213) 972-5050   verej.janoyan@lacity.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TLSP
$7,191 $30 $7,221
Non-bond Funding
State/Federal*
$0 $0 $0
Local**
$677 $0 $677
Private***
$0 $0 $0
 
Total**** $7,868 $30 $7,898

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$677 $0 $677 $677 $677 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$7,191 $30 $7,221 $7,221 $7,221 $0
 
Total* $7,868 $30 $7,898 $7,898 $7,898 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
01/17/2008 

01/17/2008 
 

 
01/17/2008 

01/17/2008 
100  01/14/2008 

01/17/2008 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/30/2008 

05/30/2009 
 

01/19/2011 
07/30/2008 

06/30/2009 
100  06/11/2008 

05/30/2009 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
06/30/2009 

07/30/2012 
01/19/2011 

01/19/2011 
07/01/2010 

08/01/2013 
100  07/01/2010 

11/01/2013 


-3 
Begin Closeout Phase

End Closeout Phase
07/30/2012 

01/30/2013 
 

 
08/01/2013 

10/01/2013 
100  12/01/2013 

06/01/2014 
-4 

-8 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Peak Delay Time Saving(minutes) 64512
Peak Period Time Savings (minutes) 1-13%

Bond Funding Cost
Adopted:
$7,191,000
Current Approved:
$7,221,000
Actual Expenditures:
$7,220,700

 

Status as of December 31, 2023.