Caltrans Logo

ATSAC - San Pedro

Description: ATSAC - San Pedro

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles County
City Los Angeles
Zip Code 90012
 
Senate District
25, 28
Assembly District 54
Congressional District 36, 37
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)      7%  
Peak Delay Time Saving(minutes)  65664      
 
Project Contacts Agency Contact Person Telephone E-mail
TLSP
Los Angeles Verej Janoyan (213) 972-5050   verej.janoyan@lacity.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TLSP
$8,911 $0 $8,911
Non-bond Funding
State/Federal*
$0 $0 $0
Local**
$891 $0 $891
Private***
$0 $0 $0
 
Total**** $9,802 $0 $9,802

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$891 $0 $891 $891 $891 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$8,911 $0 $8,911 $8,911 $8,911 $0
 
Total* $9,802 $0 $9,802 $9,802 $9,802 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
01/17/2008 

01/17/2008 
 

 
01/17/2008 

01/17/2008 
100  11/03/2008 

11/25/2008 
-9 

-10 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
06/30/2008 

10/30/2008 
 

01/19/2011 
06/30/2008 

11/30/2009 
100  03/27/2008 

01/30/2009 


10 
Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
01/30/2009 

02/28/2012 
07/09/2009 

07/09/2009 
09/01/2009 

10/01/2012 
100  09/24/2009 

10/24/2012 
-1 

-1 
Begin Closeout Phase

End Closeout Phase
02/28/2012 

08/30/2012 
 

 
10/01/2012 

04/01/2013 
100  10/24/2012 

04/24/2015 
-1 

-25 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 7%
Peak Delay Time Saving(minutes) 65664

Bond Funding Cost
Adopted:
$8,911,000
Current Approved:
$8,911,000
Actual Expenditures:
$8,911,000

 

Status as of December 31, 2023.