Caltrans Logo

ATSAC - Wilmington

Description: ATSAC - Wilmington

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles County
City Los Angeles
Zip Code 90012
 
Senate District
25, 28
Assembly District 54
Congressional District 36, 37
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)      13%  
Peak Delay Time Saving(minutes)  80640      
 
Project Contacts Agency Contact Person Telephone E-mail
TLSP
Los Angeles Verej Janoyan (213) 972-5050   verej.janoyan@lacity.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TLSP
$8,405 $2,037 $10,442
Non-bond Funding
State/Federal*
$0 $0 $0
Local**
$1,247 $-0 $1,247
Private***
$0 $0 $0
 
Total**** $9,652 $2,037 $11,689

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$1,247 $-0 $1,247 $1,247 $1,247 $-0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$8,405 $2,037 $10,442 $10,441 $10,441 $1
 
Total* $9,652 $2,037 $11,689 $11,688 $11,688 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
01/17/2008 

01/17/2008 
 

 
01/17/2008 

01/17/2008 
100  11/03/2008 

11/25/2008 
-9 

-10 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
10/30/2008 

02/28/2009 
01/19/2011 

01/19/2011 
12/01/2008 

12/01/2010 
100  12/01/2008 

10/01/2010 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
05/30/2009 

06/30/2012 
01/19/2011 

01/19/2011 
07/01/2011 

04/01/2014 
100  07/07/2011 

08/07/2014 


-4 
Begin Closeout Phase

End Closeout Phase
06/30/2012 

12/30/2012 
10/31/2012 

 
07/07/2014 

01/07/2015 
75  08/07/2014 

02/15/2017 
-1 

-26 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 13%
Peak Delay Time Saving(minutes) 80640

Bond Funding Cost
Adopted:
$8,405,000
Current Approved:
$10,442,000
Actual Expenditures:
$10,441,479

 

Status as of December 31, 2023.