ATSAC-Coliseum / Florence Phase 2

Description: ATSAC-Coliseum / Florence Phase 2

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles County
City Los Angeles
Zip Code 90012
 
Senate District
22, 26
Assembly District 46, 48, 52
Congressional District 31, 35
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Peak Delay Time Saving(minutes)  77184      
Peak Period Time Savings (minutes)      77184  
 
Project Contacts Agency Contact Person Telephone E-mail
TLSP
Los Angeles Verej Janoyan (213) 972-5050   verej.janoyan@lacity.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TLSP
$8,203 $765 $8,968
Non-bond Funding
State/Federal*
$0 $0 $0
Local**
$901 $-0 $900
Private***
$0 $0 $0
 
Total**** $9,104 $764 $9,868

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$901 $-0 $900 $900 $900 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$8,203 $765 $8,968 $8,967 $8,967 $1
 
Total* $9,104 $764 $9,868 $9,868 $9,868 $1

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
01/17/2008 

01/17/2008 
 

 
01/17/2008 

01/17/2008 
100  11/03/2008 

11/25/2008 
-9 

-10 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
12/30/2008 

01/30/2010 
01/19/2011 

01/19/2011 
03/01/2010 

04/01/2011 
100  03/01/2010 

06/01/2011 


-2 
Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
05/30/2010 

06/30/2013 
01/19/2011 

01/19/2011 
07/01/2011 

07/01/2014 
100  10/10/2011 

06/18/2014 
-3 

Begin Closeout Phase

End Closeout Phase
06/30/2013 

12/30/2013 
10/31/2012 

 
11/10/2014 

05/10/2015 
100  06/18/2014 

12/15/2016 


-19 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Peak Delay Time Saving(minutes) 77184
Peak Period Time Savings (minutes) 77184

Bond Funding Cost
Adopted:
$8,203,000
Current Approved:
$8,967,800
Actual Expenditures:
$8,967,230

 

Status as of December 31, 2023.