Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Sir Frances Drake Blvd. |
Description: Sir Frances Drake Blvd.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Marin County |
City | |
Zip Code | 94939 |
Senate District |
03 |
Assembly District | 06 |
Congressional District | 06 |
Caltrans District |
04 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Peak Delay Time Saving(minutes) | 3390 | |
Peak Period Time Savings (minutes) | 20% |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
TLSP |
Marin County | Amanuel Haile | (415) 499-7137 | ahaile@co.marin.ca.us |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
TLSP |
$208 | $-8 | $200 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $0 | $0 | ||||
Local** |
$52 | $0 | $52 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $260 | $-8 | $252 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$260 | $-8 | $252 | $252 | $252 | $0 | |
Total* | $260 | $-8 | $252 | $252 | $252 | $0 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
08/30/2008 08/30/2008 |
|
08/30/2008 08/30/2008 |
100 | 12/01/2008 02/27/2009 |
-3 -6 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
06/30/2008 09/30/2008 |
|
12/01/2008 04/15/2009 |
100 | 12/01/2008 04/15/2009 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
01/30/2009 03/30/2009 |
07/24/2008 07/24/2008 |
05/30/2009 12/31/2009 |
100 | 05/01/2009 12/01/2009 |
1 1 |
Begin Closeout Phase
End Closeout Phase |
04/30/2009 05/30/2009 |
07/24/2008 |
01/30/2010 04/30/2010 |
100 | 01/01/2010 04/01/2010 |
1 1 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Peak Delay Time Saving(minutes) | 3390 | |
Peak Period Time Savings (minutes) | 20% |
Bond Funding Cost | |
---|---|
Adopted: |
$208,000 |
Current Approved: |
$200,000 |
Actual Expenditures: |
$199,639 |
Status as of December 31, 2023.