Sir Frances Drake Blvd.

Description: Sir Frances Drake Blvd.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Marin County
City
Zip Code 94939
 
Senate District
03
Assembly District 06
Congressional District 06
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Peak Delay Time Saving(minutes)  3390      
Peak Period Time Savings (minutes)      20%  
 
Project Contacts Agency Contact Person Telephone E-mail
TLSP
Marin County Amanuel Haile (415) 499-7137   ahaile@co.marin.ca.us
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TLSP
$208 $-8 $200
Non-bond Funding
State/Federal*
$0 $0 $0
Local**
$52 $0 $52
Private***
$0 $0 $0
 
Total**** $260 $-8 $252

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$260 $-8 $252 $252 $252 $0
 
Total* $260 $-8 $252 $252 $252 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
08/30/2008 

08/30/2008 
 

 
08/30/2008 

08/30/2008 
100  12/01/2008 

02/27/2009 
-3 

-6 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
06/30/2008 

09/30/2008 
 

 
12/01/2008 

04/15/2009 
100  12/01/2008 

04/15/2009 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
01/30/2009 

03/30/2009 
07/24/2008 

07/24/2008 
05/30/2009 

12/31/2009 
100  05/01/2009 

12/01/2009 


Begin Closeout Phase

End Closeout Phase
04/30/2009 

05/30/2009 
07/24/2008 

 
01/30/2010 

04/30/2010 
100  01/01/2010 

04/01/2010 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Peak Delay Time Saving(minutes) 3390
Peak Period Time Savings (minutes) 20%

Bond Funding Cost
Adopted:
$208,000
Current Approved:
$200,000
Actual Expenditures:
$199,639

 

Status as of December 31, 2023.